1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When does a Developer become accountable for the value of a Product Backlog item selected for the Sprint?
During the Daily Scrum.
Never. The entire Scrum Team is accountable for creating value every Sprint.
Whenever a team member can accommodate more work.
At the Sprint Planning Event.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is Scrum?
a lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems
A framework within which people can address complex adaptive problems, while productively and creatively delivering products of the highest possible value
A complete methodology that defines how to develop software
A cookbook that defines best practices for software development
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Scrum pillars are:
Empiricism, Lean thinking, Transparency
Commitment, Focus, Openness, Respect, Courage
Adaptation, Empiricism, Respect
Transparency, Inspection, Adaptation
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
The Scrum Team consists of
Product Owner
Scrum Master
Project Manager
Developers
Testers
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Scrum Values:
Empiricism, Focus, Openness, Respect, Commitment
Focus, Respect, Courage, Lean thinking, Openness
Respect, Courage, Openness, Commitment, Focus
Commitment, Focus, Openness, Respect, Bravery
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the Definition of Done
a formal description of the state of the Increment when it meets the quantity measures required for the product
defines the criteria that a specific user story has to meet before being considered for estimation or inclusion into a sprint
a formal description of the state of the Increment when it meets the quality measures required for the product
a formal description of the state of the Increment when it meets everybody's expectations
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Increment
is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together
must be usable
only one Increment may be created within a Sprint
may be delivered to stakeholders prior to the end of the Sprint
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?