J808 LO1.3 Inputs and Outputs of each phase

J808 LO1.3 Inputs and Outputs of each phase

10th - 11th Grade

20 Qs

quiz-placeholder

Similar activities

Cambridge Nationals IT LO1/LO2 (1)

Cambridge Nationals IT LO1/LO2 (1)

10th - 11th Grade

20 Qs

Cambridge Nationals LO1

Cambridge Nationals LO1

10th Grade

20 Qs

The Project Life Cycle Quiz

The Project Life Cycle Quiz

11th - 12th Grade

21 Qs

IGCSE | 0417 | System Life Cycle - PG 169

IGCSE | 0417 | System Life Cycle - PG 169

10th Grade

16 Qs

Computer Software Maintenance

Computer Software Maintenance

9th - 12th Grade

15 Qs

G10 REVISION IGCSE CH 7 Documentation & Evaluation

G10 REVISION IGCSE CH 7 Documentation & Evaluation

10th Grade

20 Qs

SDLC

SDLC

7th Grade - University

15 Qs

Cambridge Nationals IT L6

Cambridge Nationals IT L6

11th Grade

20 Qs

J808 LO1.3 Inputs and Outputs of each phase

J808 LO1.3 Inputs and Outputs of each phase

Assessment

Quiz

Computers

10th - 11th Grade

Hard

Created by

David Anderson

Used 28+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are INPUTS to the Initiation phase?

User requirements

Phase review

User documentation

Test plan

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are INPUTS to the Initiation phase?

User constraints

User documentation

Phase review

Test plan

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are INPUTS to the planning phase?

Test plans

Feasibility report

Constraints list

User documentation

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are INPUTS to the planning phase?

Legislation implications

User documentation

Test plans

Phase review

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are INPUTS to the execution phase?

Feasibility report

Project plan

Phase review

Test results

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are INPUTS to the execution phase?

Test plan

Constraints list

Phase review

User documentation

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following are INPUTS to the execution phase?

Constraints list

Phase review

User documentation

Legislation implications

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?