A project manager begins the initial planning of a new project. After reviewing the project charter and speaking with the project sponsor and key stakeholders, the project manager selects a predictive project life cycle. How will the selection of this life cycle shape the way the project is carried out? (Choose three)
Study Group PMP Chapter 4 Project Integration Management

Quiz
•
Education
•
KG
•
Hard
quiz eNetwoQ
Used 32+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
2 mins • 1 pt
Cost and time will be fixed, and the project scope will be allowed to vary.
The requirements will be determined upfront before the project execution begins.
Business value will be delivered to the customer frequently rather than just at the end of the project.
A single final product will be delivered at the end of the project.
Changes will be constrained to the extent possible.
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Once a month, you attend a steering committee meeting to report on project status as specified in the communications management plan. During the meeting, the committee members challenge you on the productivity of your project team, pointing out that your team has a velocity of 40 story points per sprint, while another project team is averaging 80 points per sprint. What is your best course of action?
During the next sprint planning meeting, direct your team to complete 80 story points for the sprint
Repeat the Acquire Resources process to double the size of the team to achieve 80 story points per sprint
Submit a change request to update the project schedule with the actual velocity of the team
Take the opportunity to coach the steering committee members on the proper use of the velocity metric
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You are assisting a project sponsor with the development of a document, which authorizes a product development project. Currently, you need to identify the project's key deliverables for inclusion in the document. What might you do to obtain this information?
Ask the project sponsor for a copy of the project charter
Research the company's organizational process assets
Invite the project sponsor and other key stakeholders to join a conference call
Look at the project scope statement
4.
MULTIPLE SELECT QUESTION
2 mins • 1 pt
You are in the process of leading and performing the work as outlined in the project management plan. As part of this process, you have successfully inspired and motivated your scrum team through servant leadership to produce project deliverables at a rapid pace. As a result, the project is trending to meet and exceed the performance measurement baseline. What activities might you need to perform as part of this process? (Choose two)
Seek approval for the project charter
Implement approved change requests
Identify a comprehensive list of project stakeholders
Facilitate the daily standup meetings
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A project manager has diligently captured the knowledge gained from each iteration retrospective and recorded the information in the lessons learned register. After the project retrospective, the project manager finalizes the lessons learned register and transfers the information to the lessons learned repository as specified in the project management plan. However, when other project teams review the lessons learned as part of planning their projects, some of the information is misinterpreted, and knowledge is lost. How might the project manager have avoided this situation?
Ensured that the tacit knowledge gained during the project is recorded and codified in the lessons learned repository
Updated the organizational process assets with the knowledge gained from the project as part of project closure
Invited the other project managers to attend the project retrospective so the tacit knowledge can also be transferred
Developed a more robust knowledge management plan as part of the Plan Knowledge Management process
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A project to build a radio tower is underway when the team determines that the current transmitter only has a 75-mile range, which is 25 miles shorter than the required 100-miles range. The team requests that a more powerful transmitter be purchased. There is pressure from stakeholders to maintain the current schedule, and the project manager knows that going through the formal, lengthy change control process would cause significant schedule delays. What should the project manager do next?
Purchase the required transmitter
Submit a change request
Re-do the equipment test
Crash the project schedule
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A project will use an adaptive approach to prepare plans, develop the product, and monitor progress. Initiating and closing processes, however, will have to be managed traditionally due to the constraints imposed by the organization. In this hybrid environment, the project manager decides to use information radiators. What is the most likely reason behind the project manager's decision?
To inform project stakeholders about the progress the team made during the latest iteration retrospective meeting
To communicate progress, share issues, drive continuous improvement activities, and manage stakeholder expectations
To share information with prospective sellers and explain the roles and responsibilities of the team and project stakeholders
To document lessons learned throughout the project while preparing plans, developing the product, and monitoring progress
Create a free account and access millions of resources
Similar Resources on Quizizz
10 questions
PMP Exam Preparation Mentoring - Agile Session

Quiz
•
KG
10 questions
PMP ExamStudy Group - Project Cost Management

Quiz
•
KG
12 questions
¿Estás listo para certificarte?

Quiz
•
Professional Development
10 questions
PMP Exam Study Group - Chapter 6 Schedule

Quiz
•
KG
10 questions
LO1 OB

Quiz
•
University
10 questions
PMP Exam Preparation - Ch Communication and Stakeholder

Quiz
•
KG
10 questions
PMP Exam Mentoring - Ch 6 Project Schedule Management

Quiz
•
KG
10 questions
Digital Skills Quiz

Quiz
•
12th Grade
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade
Discover more resources for Education
10 questions
Identifying equations

Quiz
•
KG - University
15 questions
Music 2016

Quiz
•
KG - 12th Grade
44 questions
logos

Quiz
•
KG - University
20 questions
Disney Characters

Quiz
•
KG
20 questions
Kids shows

Quiz
•
KG
20 questions
Guess that Disney

Quiz
•
KG - 5th Grade
20 questions
Cartoon Characters!

Quiz
•
KG - 5th Grade