1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You gave the responsibility of collecting requirement from project stakeholder to four of your team members. After starting the requirement collection process, one of your team members left the job and the requirements could not be compiled properly. Initially, you did not notice this, however, during a product review, a few stakeholders told you that some of the features in the product were not requested by them. Therefore, to verify their comments you review the product requirements and identify the issue.
A. Scope creep
B. Scope slippage
C. Gold Scope
D. Opportunity
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
During the planning phase, you have created the WBS for the work that you are about to complete. However, because of a lack of information you are not able to create the WBS for the rest of the work, so you leave it until you get the correct and detailed information. This is an example of:
A. Iterative development approach
B. Improper collecting requirement process
C. Rolling wave planning
D. Improper scope statement
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
The client informs you that he noticed some parts of the work are not being completed by your team. You ensure him that you will look into it and give a proper response after verifying the facts. Which document will you refer to verify it?
A. Project scope statement
B. WBS dictionary
C. Schedule baseline
D. WBS
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
As the project manager for a large, complex project, you have been getting complaints from your team, including some of the management team, about all the time being spent on planning. You know that by spending time following the appropriate planning process, you can prevent many problems during execution. This will save time in the later stages of the project. One of the primary complaints you were hearing is related to the time it takes to create the Work Breakdown Structure (WBS). You are explaining the importance of the WBS to your project team members. Which of the following statements about the WBS is incorrect?
A. it is a hierarchical decomposition of Project work
B. Planned work contained in the lowest level WBS components are called WBS dictionaries.
C. The WBS subdivides the project work into smaller, more manageable pieces of work
D. The WBS organizes and defines the total scope of the project work
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
While finalizing the WBS, you assign each work package to a control account and establish a unique identified for the same work from a code of account. These identifiers help you find a hierarchical sum of costs, schedule, etc. Which statement is true about the WBS?
A. It contains all project work
B. It authorizes the project manager
C. It is a hierarchy of project staft
D. It is a hierarchical breakdown of project resources
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
During the collect requirement process, an influential stakeholder requested a Feature which was rejected. During the project execution, you notice that you have an opportunity to incorporate the requirement of this stakeholder into product and it will cost you nothing. By doing so, the stakeholder will be pleased and may help you in your next assignment. This is an example of:
A. Scope creep
B. Scope slippage
C. Gold plating
D. Opportunity
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
In the the create WBS process, you sub-divide project deliverables and project work into smaller and more manageable components. The output of this process is the Scope Baseline and Project document updates. Which of the following truly represents the scope baseline?
A. Scope statement, Scope management plan, Schedule baseline
B. Scope statement, WBS, WBS dictionary
C. WBS, WBS dictionary, Risk Register
D. Scope statement, WBS, Schedule baseline
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
11 questions
Reading Vocabulary
Quiz
•
5th Grade
11 questions
Otter
Quiz
•
4th - 6th Grade
15 questions
Lugares na cidade Recuperação
Quiz
•
9th Grade
11 questions
Animated Opening Title
Quiz
•
KG - 3rd Grade
13 questions
General knowledge
Quiz
•
9th - 12th Grade
10 questions
SDG Intro Test
Quiz
•
12th Grade
9 questions
SALES G's & S's
Quiz
•
University
14 questions
Unit 4, AOS 2 2020
Quiz
•
11th - 12th Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for Education
20 questions
Place Value
Quiz
•
KG - 3rd Grade
6 questions
3.3 Magnets
Quiz
•
KG
20 questions
Ch. 7 Quadrilateral Quiz Review
Quiz
•
KG - University
12 questions
HOMOPHONES
Lesson
•
KG - 4th Grade
10 questions
Long i- igh, ie, and y Quiz
Quiz
•
KG - 3rd Grade
12 questions
Quarter Past, Half Past, and Quarter To
Quiz
•
KG - 12th Grade
20 questions
Capitalization in sentences
Quiz
•
KG - 4th Grade
14 questions
Reference Sources
Lesson
•
KG - 3rd Grade