PMP Exam Exercise #1_50QS

PMP Exam Exercise #1_50QS

KG - 5th Grade

50 Qs

quiz-placeholder

Similar activities

ITE 2-MIDTERM LONGQUIZ

ITE 2-MIDTERM LONGQUIZ

University

50 Qs

PRE FINAL EXAM IN FNABM 4

PRE FINAL EXAM IN FNABM 4

University

50 Qs

Culinary Foundations Ch. 1-5 Test

Culinary Foundations Ch. 1-5 Test

10th - 12th Grade

50 Qs

untitled

untitled

Professional Development

52 Qs

DCET PMS 1-50

DCET PMS 1-50

University

50 Qs

Quiz - Tutorial Week 10

Quiz - Tutorial Week 10

University

50 Qs

SAD_MOD3_4

SAD_MOD3_4

2nd Grade

53 Qs

Midterm Revision

Midterm Revision

University

55 Qs

PMP Exam Exercise #1_50QS

PMP Exam Exercise #1_50QS

Assessment

Quiz

Other

KG - 5th Grade

Medium

Created by

Agus Soleh

Used 16+ times

FREE Resource

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager discovers that the vendor did not perform software technical testing. Which document confirms whether the vendor should do this testing?

Procurement management plan

Statement of work (SOW)

Scope management plan

Product scope description

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager delivered the final project report and is ready to close the project. The company is anxious to start an important project and asks the project manager to start the new assignment immediately.

What final action should the project manager take before moving to the new project?

Obtain final approval of project deliverables and confirm whether changes were implemented.

Confirm whether project documentation has been filed according to company standards.

Ensure that procurements have been reviewed and that contracts have been closed.

Compile the lessons learned during all project stages and hold a meeting to review them.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

To reduce a product's defect ratio, a corrective action is being implemented. The project manager then discovers that the corrective action is insufficient and that the team needs to resolve additional technical issues.

What should the project manager do next?

Issue a change request.

Schedule a change control board (CCB) meeting.

Arrange an emergency stakeholder meeting.

Prepare a trend analysis

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During execution of a critical project, a project manager is removed due to continuous customer and stakeholder complaints about lack of communication. What should the new project manager do first?

Manage stakeholder engagement.

Review the project management plan.

Use influencing to obtain project support

Meet with the project team.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

After performing the program evaluation and review technique (PERT), the following information was produced. Using a beta distribution, how many hours is the weighted average activity time?

4.66

5.16

5.33

6.16

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A vendor supplies equipment for several of a company's projects. The vendor informs one project manager that the project's equipment can be delivered earlier than anticipated. The project manager recognizes that this is an opportunity to complete the project ahead of schedule.

What should the project manager do next?

Request management approval

Use the equipment offered.

Revise the project schedule.

Determine if there is a risk.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a project's execution phase, a developer suggests a design change that will improve system performance without incurring additional costs. What should the project manager do first?

Analyze the work performance data to ensure that there will be no negative impact.

Ask the developer to implement the change without negatively impacting the schedule.

Ask the technical manager to review the suggestion.

Document the suggestion and implement the Perform Integrated Change Control process.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?