PMP ExamStudy Group - Project Cost Management

PMP ExamStudy Group - Project Cost Management

KG

10 Qs

quiz-placeholder

Similar activities

MHS Capacities Quizizz

MHS Capacities Quizizz

9th - 12th Grade

12 Qs

PMP Study Group - Agile

PMP Study Group - Agile

KG

10 Qs

Project Management 1.06 Video

Project Management 1.06 Video

10th Grade

11 Qs

PMP Exam Mentoring Ch 7 Project Cost Management

PMP Exam Mentoring Ch 7 Project Cost Management

KG

10 Qs

PMP Exam Preparation - Ch 12 Project Procurement Management

PMP Exam Preparation - Ch 12 Project Procurement Management

KG

10 Qs

PMP Exam Mentoring - Ch 6 Project Schedule Management

PMP Exam Mentoring - Ch 6 Project Schedule Management

KG

10 Qs

Educ. 605 Unit IV Project Budgeting and Fund Raising

Educ. 605 Unit IV Project Budgeting and Fund Raising

Professional Development

6 Qs

LO2 Project Life Cycles Quiz

LO2 Project Life Cycles Quiz

Professional Development

10 Qs

PMP ExamStudy Group - Project Cost Management

PMP ExamStudy Group - Project Cost Management

Assessment

Quiz

Education

KG

Hard

Created by

quiz eNetwoQ

Used 29+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

1. Shortly before rolling out a product in a newly targeted country, a company realizes that the product does not fully complywith local data privacy laws. Due to budget constraints, the company has to decide on whether to pay incompliance finesor do rework. Part of the rework would involve adding new user stories to the product backlog.<br />In this situation, which of the following is most likely to help?
A. Refactoring
B. Personas
C. A phase gate
D. Fast tracking

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

2. A team of efficiency experts hired by your company has concluded that the transportation costs associated with yourproject are excessive. You have been requested by the sponsor to cut the costs.<br />What is your best course of action?
A. Perform a root cause analysis
B. Conduct a cost reduction analysis
C. Carry out a trend analysis
D. Fast tracking

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

3. You are planning a research and development project, and you need to determine how the project costs will beestimated, budgeted, managed, monitored, and controlled. To complete this process, you need to know if there are anypreapproved financial resources from which the detailed project costs can be developed.<br />What should you do next?
A. Consult the cost management plan
B. Review the project charter
C. Examine the basis of estimates for the project
D. Check the cost baseline

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

4. You have just performed a variance analysis for your project and determined that the CPI is 0.9 and the SPI is 1.2. Thisproject is considered high profile, and it is critical that you meet all project objectives.<br />Based on the variance analysis, what should you do next?
A. Reduce the product features to bring costs back into alignment with the project budget
B. Crash the schedule to bring the schedule in line with project objectives
C. Conduct further research to isolate and understand the variance from the cost baseline
D. Release one of the developers to reduce costs

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

5. A company must decide between renovating an existing building or constructing a new one. Each approach would requirean initial investment of $250,000. The renovation has a payback period of 2.5 years whereas the new construction has apayback period of 4.5 years. Your company president would need to make the final decision.<br />All else being equal, which approach should you recommend as the better investment?
A. The construction of a new office building
B. The renovation of the current office building
C. There is not enough information to make a decision
D. Both options are equal since the initial investment is the same

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

6. You are managing a hotel construction project, and you have asked your project team to calculate the current earnedvalue metrics to determine the project performance. Your team reports back that the project's to-complete performanceindex (TCPI) is 0.9 based on the budget at completion (BAC).<br />Which of the following is true regarding your project's current situation as reflected by this TCPI value?
A. The project is within budget
B. The project is over budget
C. The project is behind schedule
D. The project is ahead of schedule

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

7. During project initiation, the project manager had provided an initial estimate of $250,000 with a range of -25% to +75%.The project is now in planning, and, as part of the Estimate Costs process, the project manager has to refine this estimateto a much narrower range.<br />How should the project manager determine the estimating methods that can be used and the accuracy required for thecost estimate?
A. Review the cost management plan
B. Examine the basis of estimates
C. Contact the finance department
D. Check the project charter

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?