Agile_forum_05_08

Agile_forum_05_08

1st - 3rd Grade

25 Qs

quiz-placeholder

Similar activities

XI IPA PJOK

XI IPA PJOK

1st Grade

20 Qs

PM - CH3 Recap - T/F

PM - CH3 Recap - T/F

1st - 3rd Grade

20 Qs

Quel est son sport ?

Quel est son sport ?

1st - 10th Grade

20 Qs

Clevered-Halloween-Scratch

Clevered-Halloween-Scratch

1st - 5th Grade

25 Qs

Metodologías para la Innovación

Metodologías para la Innovación

1st - 3rd Grade

20 Qs

Stay Fit To Be Great

Stay Fit To Be Great

1st - 3rd Grade

20 Qs

Mini SG PMP

Mini SG PMP

3rd Grade

20 Qs

Synonyms & Antonyms

Synonyms & Antonyms

2nd Grade

20 Qs

Agile_forum_05_08

Agile_forum_05_08

Assessment

Quiz

Other

1st - 3rd Grade

Hard

Created by

Anna Bulanda

Used 2+ times

FREE Resource

25 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which of the following projective practices are mentioned in the Scrum Guide (choose all that apply)?

Burn down charts

Gantt charts

Cumulative Flows

Burn up charts

WIP

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

At the Sprint Planning Developers don't want to engage with the stakeholders. How could you as Scrum Master deal with this?

Explain the importance of collaboration between business and Developers.

Give immediate feedback to the team.

Seek ways to improve the team dynamics to prevent this from happening again.

Alll of the above.

3.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Developers are working on an existig feature. They realise that it has been poorly designed and will be difficult to maintain. What should they do? (choose all that apply)

Cancel the Sprint

Mention it to the Scrum Master and Product Owner

Consider re-factoring

Nothing

Apply TDD

4.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Scrum relies on transparency: (choose all that apply)

To have a sound basis for decisions to optimize value.

To have a sound basis for decisions to control risk.

To allow the Product Owner calculate his ROI using tracked metrics during the Sprint.

To continuously improve the control of the Developers by the Scrum Master.

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following statement is false?

Scrum optimizes quality.

Scrum optimizes predictability.

Scrum optimizes change.

Scrum optimizes risk.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

When multiple Scrum Teams are building one product, the teams should self-organise to create:

An integrated increment each Sprint.

An incerement at every Sprint that is not integrated. This avoids complex dependencies.

An increment that is ready for integration.

None of the above.

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

How does the Scrum Master serves the organisation? (choose all that apply)

Monitoring the Sprint Backlog to assure it is in line with the organisational objectives.

Establish policies and procedures to enforce the adaption of Scrum in the organisation.

Working with other Scrum Masters to increase the effectiveness of the apllication of Scrum in the organisation.

Causing change that increases the productivity of the Scrum Team.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?