1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.
What kind of estimate is this?
PMP Exam Mentoring Ch 7 Project Cost Management
Quiz
•
Education
•
KG
•
Medium
quiz eNetwoQ
Used 13+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.
What kind of estimate is this?
A. Definitive estimate
B. Rough order of magnitude estimate
C. Wide Estimate
D. Plan Estimate
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
2. A team of efficiency experts hired by your company has concluded that the transportation costs associated with yourproject are excessive. You have been requested by the sponsor to cut the costs.
What is your best course of action?
A. Perform a root cause analysis
B. Conduct a cost reduction analysis
C. Carry out a trend analysis
D. Fast tracking
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
3. You are planning a research and development project, and you need to determine how the project costs will beestimated, budgeted, managed, monitored, and controlled. To complete this process, you need to know if there are any preapproved financial resources from which the detailed project costs can be developed.
What should you do next?
A. Consult the cost management plan
B. Review the project charter
C. Examine the basis of estimates for the project
D. Check the cost baseline
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
4. While working on a game design project, the project sponsor has asked the project manager that to ensure that his estimates are very precise.
What estimating technique should the project manager use?
A. Analogous Estimate
B. Bottom-up estimating
C. Accuracy Estimating
D. Oversight Estimating
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
5. A company must decide between renovating an existing building or constructing a new one. Each approach would requirean initial investment of $250,000. The renovation has a payback period of 2.5 years whereas the new construction has apayback period of 4.5 years. Your company president would need to make the final decision. All else being equal, which approach should you recommend as the better investment?
A. The construction of a new office building
B. The renovation of the current office building
C. There is not enough information to make a decision
D. Both options are equal since the initial investment is the same
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
6. You are managing a hotel construction project, and you have asked your project team to calculate the current earnedvalue metrics to determine the project performance. Your team reports back that the project's to-complete performanceindex (TCPI) is 0.9 based on the budget at completion (BAC).
Which of the following is true regarding your project's current situation as reflected by this TCPI value?
A. The project is within budget
B. The project is over budget
C. The project is behind schedule
D. The project is ahead of schedule
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
7. During project initiation, the project manager had provided an initial estimate of $250,000 with a range of -25% to +75%.The project is now in planning, and, as part of the Estimate Costs process, the project manager has to refine this estimateto a much narrower range.
How should the project manager determine the estimating methods that can be used and the accuracy required for thecost estimate?
A. Review the cost management plan
B. Examine the basis of estimates
C. Contact the finance department
D. Check the project charter
11 questions
IPM - Chapter 7 (Cost Management)
Quiz
•
University
10 questions
PMP Exam Mentoring - Ch 6 Project Schedule Management
Quiz
•
KG
11 questions
Project Management 1.06 Video
Quiz
•
10th Grade
11 questions
Project Planning
Quiz
•
1st - 5th Grade
10 questions
Topic 1- Introduction to estimating
Quiz
•
University
10 questions
PMP Exam Study Group - Chapter 6 Schedule
Quiz
•
KG
7 questions
Project Management & Leadership
Quiz
•
University
12 questions
MHS Capacities Quizizz
Quiz
•
9th - 12th Grade
15 questions
Multiplication Facts
Quiz
•
4th Grade
20 questions
Math Review - Grade 6
Quiz
•
6th Grade
20 questions
math review
Quiz
•
4th Grade
5 questions
capitalization in sentences
Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance
Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions
Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines
Quiz
•
Professional Development
12 questions
Dividing Fractions
Quiz
•
6th Grade