10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What is the purpose of project management?

Plan, organise, budget and control the project, so it meets the needs of the customer within the constraints given.

Plan, organise, budget and control the project, so it goes against the needs of the customer within the constraints given.

2.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What is a sub-contractor?

an individual or business paid to work on a project, usually known as a third party, and an employee of the company that the project is being carried out for.

an individual or business paid to work on a project, usually known as a third party, and not an employee of the company that the project is being carried out for.

an individual and business paid to work on a project, usually known as a third party, and an employee of the company that the project is being carried out for.

3.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What is a project budget?

Is a sum of money allocated to undertake and complete a task.

Is a partial sum of money allocated to undertake and complete a task.

Is a sum of money allocated to complete a part of a task.

4.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What is a PM?

The Planning Manager (PM) is responsible for planning the project and overseeing its execution within the constraints of the budget.

The Project Manager (PM) is responsible for overseeing the projects execution within the constraints of the budget.

The Project Manager (PM) is responsible for planning the project and overseeing its execution within the constraints of the budget.

5.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What is contingency mean?

Uanticipated allowance made for expected future events.

Anticipated allowance made for unexpected future events

Unanticipated allowance made for expected future events

Anticipated allowance made for expected future events

6.

MULTIPLE SELECT QUESTION

15 mins • 1 pt

What sort of unexpected events might result in using a contingency fund?

Rising costs of labour

Bankruptcy

Delays in supplies

Need for additional resources

7.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Why would a PM set milestones and deadlines?

PM can organise resources in accordance with each stage and keep better control over the budget

PM can organise people in accordance with each stage and keep better control over the budget

PM can organise resources in accordance with the overall project

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Instructional Technology