Networks & Critical Path analysis
Authored by Marlene Cooper
Mathematics
12th Grade
Used 76+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
9 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
The diagram shows the activities required to complete a factory process. A forward scan has been completed for the process.
The duration of activity H is missing. What value should appear?
13
14
15
16
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a factory process. A forward scan has been completed for the process.
When a backward scan is completed, what is the value of X?
20
22
24
25
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a factory process. A forward scan has been completed for the process.
What is the critical path?
ABJ
AEGJ
CDGJ
CDHJ
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a task from start to finish and each activity has the duration (in days) shown beside it.
What is the EST (Earliest starting time) for activity Q?
23
27
28
29
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a process from start to finish and each activity has a duration (in days) shown beside it.
What is the critical path?
IKLPQ
IJMPQ
IJMNOQ
IKLNOQ
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a process from start to finish and each activity has a duration (in days) shown beside it.
What is the float time for activity K?
1 day
2 days
3 days
4 days
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A network flow diagram is shown.
Find the total weight of the cut labelled 1.
88
96
98
104
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?