Unit 3 - A1, A2

Unit 3 - A1, A2

11th - 12th Grade

13 Qs

quiz-placeholder

Similar activities

DofE training refresher

DofE training refresher

10th - 12th Grade

18 Qs

Football Quiz

Football Quiz

KG - Professional Development

15 Qs

Exoictic cars.

Exoictic cars.

5th Grade - Professional Development

10 Qs

Ohio Valley College of Technology

Ohio Valley College of Technology

KG - University

10 Qs

ONLINE PLATFORMS

ONLINE PLATFORMS

11th - 12th Grade

10 Qs

Disney Personalities

Disney Personalities

5th Grade - University

15 Qs

SciVis I Unit 6 B

SciVis I Unit 6 B

9th - 12th Grade

15 Qs

Thickening Agents and Methods

Thickening Agents and Methods

11th - 12th Grade

10 Qs

Unit 3 - A1, A2

Unit 3 - A1, A2

Assessment

Quiz

Instructional Technology, Other

11th - 12th Grade

Easy

Created by

Alex McCluskey

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What is the purpose of project management?

Plan, organise, budget and control the project, so it goes against the needs of the customer within the constraints given.

Plan, organise, budget and control the project, so it meets the needs of the customer within the constraints given.

2.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What is a project budget?

Is a partial sum of money allocated to undertake and complete a task.

Is a sum of money allocated to undertake and complete a task.

Is a sum of money allocated to complete a part of a task.

3.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What does contingency mean?

An anticipated allowance made for unexpected future events

An unanticipated allowance made for expected future events.

An anticipated allowance made for expected future events

An unanticipated allowance made for expected future events

4.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Why would a PM set milestones and deadlines?

PM can organise resources in accordance with the overall project

PM can organise people in accordance with each stage and keep better control over the budget

PM can organise resources in accordance with each stage and keep better control over the budget

5.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Why is an interim review important?

Enables the team to organise the entire project.

Enables the team to organise the work involved in each step in the sequence.

6.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Quality frameworks are designed to...

Support quality of checks of hardware systems against the objectives and required deliverables of a project

Support quality of checks of both hardware systems and software products against the objectives and required deliverables of a project

Support quality of checks of software products against the objectives and required deliverables of a project

7.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

What are deliverables?

The agreed outcomes of each milestone

The agreed outcomes of each task

The agreed outcomes of the project

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?

Discover more resources for Instructional Technology