IT Consulting 2 - Technology change management

Authored by Vladimir Ryabov

Computers

University

Used 6+ times

IT Consulting 2 - Technology change management
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Consider Gleicher's formula. When the client says, "We are happy with the way things are", it indicates deficiencies in:

(Select the correct answer)

Practical clear steps towards the desired state

The level of dissatisfaction with the status quo

The clear desired state

The costs of change

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Consider Gleicher's formula. Explaining to the client how improvements can be achieved shows ...

(Select the correct answer)

The level of dissatisfaction with the status quo

The clear desired state

Practical clear steps towards the desired state

The costs of change

3.

MULTIPLE SELECT QUESTION

1 min • 1 pt

Select all possible components of a technology change project

IT infrastructure

IT management processes

Training

IT system(s)

Business processes

4.

MULTIPLE SELECT QUESTION

1 min • 1 pt

What does recommending relevant solutions to the client mean?

(Select all relevant answers)

The consultant should like that particular solution

The solution is economically justified

The solution corresponds to the capabilities of the client organisation

The management of the client organisation should like that particular solution

5.

MULTIPLE SELECT QUESTION

1 min • 1 pt

The recommended technology solution should be economically justified. What does this mean?

(Select all relevant components)

The client organisation can afford this solution financially

The solution should typically (however not always!) be less costly than the problem is

The consultant recommends the solution they know about

The costs of the solution and the associated organisational changes are estimated

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What are the critical activities in a technology change project?

The most expensive activities

Activities involving many stakeholders

Elements of the project that will ensure the achievement of the project goals

Activities requiring the involvement of the organisational management

7.

MULTIPLE SELECT QUESTION

1 min • 1 pt

Select the business process measures that can be considered by a consultant when defining performance targets

Time

IT equipment

Costs

Resources

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?