Power System Operator

Power System Operator

Professional Development

38 Qs

quiz-placeholder

Similar activities

Quizomania Round 1

Quizomania Round 1

Professional Development

40 Qs

BD.18-01-22.06-SG

BD.18-01-22.06-SG

Professional Development

40 Qs

Chapter 17 Science

Chapter 17 Science

KG - Professional Development

40 Qs

Philippine Electrical Code (PEC-1A)

Philippine Electrical Code (PEC-1A)

Professional Development

35 Qs

ELECTRICIAN THEORY

ELECTRICIAN THEORY

Professional Development

40 Qs

LV08 Chassis A

LV08 Chassis A

Professional Development

34 Qs

ER - Endocrine

ER - Endocrine

Professional Development

37 Qs

Ecuación de Difusión - Almacenamiento y Daño

Ecuación de Difusión - Almacenamiento y Daño

University - Professional Development

39 Qs

Power System Operator

Power System Operator

Assessment

Quiz

Physics, Science

Professional Development

Easy

Created by

vamshi ballikonda

Used 1+ times

FREE Resource

38 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Energy consumption per unit of GDP is called as:
Energy Ratio
Energy Intensity
Per Capita Consumption
None

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Star rating is a part of ______ programme of BEE
DSM
BLY
S&L
None

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As per IEGC (latest amendment) “frequency band” in Hz is
49.90 – 50.05
49.5 – 50.3
49.7 – 50.2
49.5 – 50.2

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Action for non-compliance of IEGC may be taken by
Central Electricity Authority (CEA) on recommendation by RPC or RLDC
Regional Power Committee (RPC) on report by RLDC
Central Electricity Regulatory Commission(CERC) on report by RPC and RLDC only
Central Electricity Regulatory Commission(CERC) on report by any person or suo-motu

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A part of the grid can be deliberately isolated from the rest of the National/Regional grid, only
under an emergency, or to prevent collapse of grid
for safety of human life
when serious damage to a costly equipment is imminent and such isolation would prevent it,
All of these

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As per IEGC, restricted governor mode of operation is to be implemented for generating stations synchronized with grid ( with exceptions mentioned in IEGC) of the following category.
All thermal generating units of 200 MW and above
All hydro units (except those with upto three hours pondage) of 10 MW and above,
Thermal units >=200MW and Hydro units >=10MW owned by central sector Generating companys
All coal/lignite based thermal generating units of 200MWand above, open cycle gas turbine/CCGT of capacity more than 50MW and all hydro units of 25MW and above

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As per stipulations in IEGC, the control Area jurisdiction of any generating station
Can not change once decided
May be in one control area (i.e. SLDC) at one point of time and another control area (i.e. RLDC) at another point of time
As decided by RPC
As decided by RLDC

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?