1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

127. Project Quality Management includes the processes for incorporating the organization's quality policy regarding planning, managing, and controlling project and product quality requirements in order to:

A. Meet stakeholders' objectives

B. Improve process capability

C. Control products, services and results

D. Meet standards of performance for the project team

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

128.Quality and grade are not the same .A fundamental distinction is that:

A. Quality as a delivered performance or result isthe degree to which a set of inherent characteristics fulfills requirements; grade as a design intent is a category assigned to deliverables having the same functional use but different technical characteristics.

B. A quality level that fails to meet quality requirements may not be a problem; a low grade ofquality is always a problem.

C. Delivering the required levels of quality is not included in the responsibilities of the project manager and the project team.

D. Delivering the required levels of grade is not included in the responsibilities of the project manager and the project team.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

129.Understanding, evaluating, defining, and managing requirements areessential to satisfying:

A. Customer expectations.

B. The scope statement.

C. Upper management.

D. Functional requirements.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

130.All of the following are primary benefits of meeting quality requirements EXCEPT:

A. Less rework.

B. Higher productivity.

C. Lower costs.

D. Fewer change orders.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

131.Inputs to control quality include all of the following EXCEPT:

A. Project management plan.

B. Quality metrics.

C. Work performance data.

D. PERT chart.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

132.The quality management plan is a component of the _____ which describes how the organization's quality policies will be implemented .

A. Project management plan

B. Program management plan

C. Project scope

D. Governance management plan

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

133.Manage quality is the process of :

A. Applying planned, systematic quality activities to ensure effective policing and conformance of the project team to the approved specifications.

B. Providing the project team and stakeholders with standards by which project performance is measured.

C. Translating the quality management plan into executable quality activities that incorporate the organization's quality policies into the project.

D. Assuring the implementation of appropriate specifications, which generally reduces the probability of the project being completed on schedule .

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?