1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following options are roles in a formal review?
Developer, Moderator, Review leader, Reviewer, Tester
Author, Moderator, Manager, Reviewer, Developer
Author, Manager, Review leader, Reviewer, Designer
Author, Moderator, Review leader, Reviewer, Scribe
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which activities are carried out within the planning of a formal review?
Collection of metrics for the evaluation of the effectiveness of the review
Answer any questions the participants may have
Definition and Verification of fulfillment of entry criteria for the review
Evaluation of the review findings against the exit criteria
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following statements CORRECTLY reflects the value of static testing?
By introducing reviews, we have found that both the quality of specifications and the time required for development and testing have increased
Using static testing means we have better control and cheaper defect management due to the ease of detecting defects later in the lifecycle
Now that we require the use of static analysis, missed requirements have decreased and communication between testers and developers has improved
Since we started using static analysis, we find coding defects that might have not been found by performing only dynamic testing
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following CORRECTLY matches the roles and responsibilities in a formal review?
Manager – Decides on the execution of reviews
Review Leader - Ensures effective running of review meetings
Scribe – Fixes defects in the work product under review
Moderator – Monitors ongoing cost-effectiveness
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
In a formal review, what is the role name for the participant who runs an inspection meeting?
Facilitator
Programmer
Author
Project manager
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You are reading a user story in the product backlog to prepare for a meeting with the product owner and a developer, noting potential defects as you go. Which of the following statements is true about this activity?
It is not a static test, because static testing involves execution of the test object
It is not a static test, because static testing is always performed using a tool
It is a static test, because any defects you find could be found cheaper during dynamic testing
It is a static test because static testing does not involve execution of the test objec
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
During a period of intensive project overtime, a system architecture document is sent to various project participants, announcing a previously unplanned technical review to occur in one week. No adjustments are made to the participants’ list of assigned tasks. Based on this information alone, which of the following is a factor for review success that is MISSING?
Appropriate review type
Adequate time to prepare
Sufficient metrics to evaluate the author
Well-managed review meeting
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?