IST - 2022

IST - 2022

University

8 Qs

quiz-placeholder

Similar activities

Avancemos 1 tener expressions

Avancemos 1 tener expressions

KG - University

12 Qs

カタカナ ナ〜ホ

カタカナ ナ〜ホ

KG - Professional Development

10 Qs

There is / There are and quantities

There is / There are and quantities

University

10 Qs

Holonyms

Holonyms

University

10 Qs

The World of English

The World of English

University

11 Qs

L2 Wrap up 1

L2 Wrap up 1

University

12 Qs

UK Culture Quiz

UK Culture Quiz

9th Grade - University

10 Qs

Greetings

Greetings

KG - University

10 Qs

IST - 2022

IST - 2022

Assessment

Quiz

World Languages

University

Practice Problem

Medium

Created by

Rui Abrantes

Used 24+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which type of organization is the Project Manager most likely to have<br />full-time project management administration staff?

Project-oriented
Organic
Balanced matrix
Hybrid

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A key output of the Identify Stakeholders process is

Change log
An agreement
A risk management plan
A stakeholder register

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Code of Ethics and Professional Conduct has as its foundation four

Respect, fairness, transparency and freedom
Responsibility, transparency, fairness and honesty
Respect, freedom, honesty and transparency
Responsibility, respect, fairness and honesty

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The document that formally authorizes a project is the:

Project SOW
Project Plan
Project Charter
Project Scope Statement

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A collection of related projects that are managed in a coordinated way to<br />obtain benefits is called a:

Suite
Program
Portfolio
Colocation

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of these is not an example of a project?

Buying clothes from the market on a special sale
Planning for your friends wedding
Building a bridge across the Amazon river
Cleaning the office building every day.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the below is a likely reason for conflict between portfolios,<br />programs, projects, and operations?

They often engage with the same stakeholders and may need to use the same resources
They are led by managers who have competing aims
Portfolios can include programs, projects, and operations, and that makes the program managers, project managers, and operations managers feel unimportant
They usually come from various organizations

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes Plan Stakeholder Management<br />process?

Creation and maintenance of relationships between the project team and stakeholders
Preventing negative stakeholders from derailing the project
Striking a balance between stakeholder needs and project needs
Focuses on from the creation of the stakeholder management strategy