LW Revised Final Review PM1

LW Revised Final Review PM1

9th - 12th Grade

40 Qs

quiz-placeholder

Similar activities

Számvitel alapjai - Számviteli alapelvek és értékelés

Számvitel alapjai - Számviteli alapelvek és értékelés

9th Grade - University

37 Qs

Accounting classification

Accounting classification

9th - 12th Grade

40 Qs

Law End of Year Review #2

Law End of Year Review #2

9th - 12th Grade

40 Qs

Inwestowanie i oszczędzanie

Inwestowanie i oszczędzanie

10th Grade

40 Qs

PENILAIAN NERACA PEMBAYARAN INTERNASIONAL

PENILAIAN NERACA PEMBAYARAN INTERNASIONAL

11th Grade

40 Qs

penataan produk

penataan produk

11th Grade

40 Qs

Personal Financial Planning

Personal Financial Planning

11th Grade

36 Qs

LW Revised Final Review PM1

LW Revised Final Review PM1

Assessment

Quiz

Business

9th - 12th Grade

Medium

Created by

Bobbie Jones

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

A project manager is at the prom and realizes that steak was delivered and not chicken. He makes the catering manager aware immediately that the steak meal is outside the project scope. Which project management process stage is Andrew in?

executing

monitoring and controlling

closing

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Brenda is meeting with her stakeholders to determine the scope of work. What process stage is she in?

initiating

executing

monitoring and controlling

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

A PM is working with her sisters to determine how much money they have spent on their parents' anniversary party to calculate the funds remaining in their budget. What process stage is she in?

initiating

executing

monitoring and controlling

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

The organizational structure in which the project manager has the greatest amount of authority is a:

functional organization.

matrix organization.

projectized organization.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

The organizational structure in which the project manager has the least amount of authority is a:

functional organization.

matrix organization.

projectized organization.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

A project manager holds a team meeting to discuss lessons learned. He is in which process stage?

closing

executing

monitoring and controlling

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Senior prom ends the large project of the junior class representatives. The group development stage when the team is broken apart is called:

forming.

adjourning.

storming.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?