CEA Final Exam Review

CEA Final Exam Review

11th - 12th Grade

34 Qs

quiz-placeholder

Similar activities

Fault finding Mock exam!

Fault finding Mock exam!

1st - 12th Grade

30 Qs

LATIH 2 A PQS SPM

LATIH 2 A PQS SPM

11th Grade

30 Qs

SEJARAH T5/B3

SEJARAH T5/B3

6th - 12th Grade

34 Qs

IED Final Exam Review

IED Final Exam Review

9th - 12th Grade

37 Qs

HUMSS 2 Semi-Final Exam

HUMSS 2 Semi-Final Exam

11th Grade

33 Qs

BC: L4.4 The Fundamental Theorem of Calculu

BC: L4.4 The Fundamental Theorem of Calculu

11th Grade

31 Qs

Financial Fitness Review

Financial Fitness Review

9th - 12th Grade

35 Qs

Soal PTS Tata Hidang

Soal PTS Tata Hidang

11th Grade

32 Qs

CEA Final Exam Review

CEA Final Exam Review

Assessment

Quiz

Other

11th - 12th Grade

Medium

Created by

Claudia Cortez

Used 19+ times

FREE Resource

34 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The main purpose of foundations is to:___________(2.3.5)

a.Provide a level, stable surface to safely support a building

b.Transfer building loads to soil

c.Anchor the building from wind, flood, and seismic loads

d.All of the above

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

What is the approximate frost depth in Noblesville, IN?

a.5 in

b.10 in

c.20 in

d.25 in

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Calculate the required concrete iIf the required total footage is 750 ft3. How many yards will be needed for concrete?

a.10 yd3

b.20 yd3

c.28.5 yd3

d.30 yd3

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Calculate the total cost of the concrete if the required total footage is 750 ft3. What will be the total cost of the concrete if concrete is $98/yd3  ?

a.$1,793.00

b.$2,793.00

c.$3,793.00

d.$4,793.00

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What will be a problem that will result from ordering too little concrete?

a.The entire pour will be completed at the same time. 

 b.An increase in  the time and cost of construction. 

c.Less cost of concrete

d.Less cost of labor

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Electricity is supplied to a building via a service drop that includes

a.Three wires

b.Two wires carry 120 volts of alternating current (AC) such that the voltages are opposite

c.One wire is neutral or ground (zero volts)

d.All of the above

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What distributes power to the building and is the main breaker that allows all power to be switched off?

a.Electrical power

b.main panel

c.electrical cables

d.None of the above

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?