1.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

In which of the following organizations is the project manager role more likely to be filled as a full-time position?

Functional

Matrix

Projectized

All

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following choices most properly reflects matching roles to responsibilities? (This question tests your past course knowledge as well as your concepts that has developed after the completion of Module 1 in this course)

Senior management: Signing the project charter, approving schedule change requests, and naming the project manager.

Project manager: Signing the project charter, approving schedule change requests, and assigning team resources to activities.

Senior management: Communicating the strategic vision, matching portfolio options to the goals, and signing the project charter.

Program manager: Coordinating multiple project dependencies, Communicating the program vision, and assigning project team members to activities.

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Which of the following statements about a project is not true?

A project can involve a single person.

A project must include all unique elements; otherwise, the work is considered ongoing operations.

A project may create a capability to provide a service.

A project may create a result, such as a research document.

4.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

In a matrix organization, more power is given to the

Functional Manager

Project Manager

Project Coordinator

Team members

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is considered to be the most useful skill for a project manager who works in a matrix environment in order to achieve project goals?

Leadership skill

Influencing

Conflict management skill

Planning skill

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Marco is an investor, and Jon is a project team member. Both have intensive technical background for the project that you are managing. However, recently they have disagreed on the next step to take for the project. They both decide to defer to whoever has the authority to make this decision. Who has the authority to decide which direction should be taken for the project?

Project manager

Stakeholders

The project team

Investors

7.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

A strategy is thought oriented.

True

False

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development