1.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
The need for __ is one of the major driving forces for communication in a project.
A. Optimization
B. Integrity
C. Integration
D. Differentiation
2.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
The customer has accepted the completed project scope. However, the lessons learned required by the project management office have not been completed. What is the status of the project?
A. The project is incomplete because it needs to be replanned
B. The project is incomplete until all project and product deliverables are complete and accepted
C. The project is complete because the customer has accepted the deliverables.
D. The project is complete because it has reached its due date.
3.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
A project is plagued by changes to the project charter. Who has the primary responsibility to decide if these changes are necessary?
A. The project manager
B. The project team
C. The sponsor
D. The stakeholders
4.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Effective project integration usually requires an emphasis on:
A. The personal careers of the team members
B. Timely updates to the project management plan
C. Effective communication at key interface points
D. Product control
5.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Integration is managed by the:
A. Project manager
B. Team
C. Sponsor
D. Stakeholders
6.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Which of the following BEST describes the project manager's role as an integrator?
A. Help team members become familiar with the project
B. Put all the pieces of a project into a cohesive whole
C. Put all the pieces of a project into a program
D. Get all team members together into a cohesive whole
7.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Which of the following BEST describes a project management plan?
A. A printout from project management software
B. A detail project schedule
C. Risk, human resource, process improvement, and other management plans
D. The project scope
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
13 questions
KUIZ PENILAIAN SELEPAS PROGRAM HRDF PENJANA
Quiz
•
1st - 3rd Grade
10 questions
comunicacion no verbal
Quiz
•
1st Grade
8 questions
Inside Solutions
Quiz
•
1st - 5th Grade
10 questions
Nutritional Quiz
Quiz
•
1st Grade
15 questions
POLYGRAPHY QUIZ#2 IN FINAL
Quiz
•
1st Grade
11 questions
Ingeniería
Quiz
•
1st - 2nd Grade
15 questions
LEA 1 QUIZ #1 IN FINAL
Quiz
•
1st Grade
14 questions
Air quality monitoring
Quiz
•
1st - 2nd Grade
Popular Resources on Wayground
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
4:3 Model Multiplication of Decimals by Whole Numbers
Quiz
•
5th Grade
10 questions
The Best Christmas Pageant Ever Chapters 1 & 2
Quiz
•
4th Grade
12 questions
Unit 4 Review Day
Quiz
•
3rd Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
15 questions
Solving Equations with Variables on Both Sides Review
Quiz
•
8th Grade
Discover more resources for Professional Development
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
16 questions
Christmas 1st grade
Quiz
•
1st Grade
10 questions
Exploring the Water Cycle
Interactive video
•
1st - 5th Grade
20 questions
Place Value
Quiz
•
KG - 3rd Grade
20 questions
Modules 4 - 6 CBA Review
Quiz
•
1st Grade
10 questions
Exploring the American Revolution
Interactive video
•
1st - 5th Grade
7 questions
Attack on Pearl Harbor for Kids | Bedtime History
Interactive video
•
1st - 12th Grade
15 questions
Addition and Subtraction Facts
Quiz
•
1st - 2nd Grade