Chapt5

Quiz
•
Professional Development
•
1st Grade
•
Medium
WS Ho
Used 2+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?
A. Critical path method
B. Flowchart
C. Precedence diagramming
D. Work breakdown structure
2.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Which of the following are GENERALLY illustrated BETTER by bar charts than network diagrams?
A. Logical relationships
B. Critical paths
C. Resource trade-offs
D. Progress or status
3.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
If the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity?
A. 1
B. 1.3
C. 6
D. 3
4.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Lag means:
A. The amount of time an activity can be delayed without delaying the project finish date
B. The amount of time an activity can be delayed without delaying the early start date of its successor
C. Waiting time
D. The product of a forward and backward pass
5.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
A project has three critical paths. Which of the following BEST describes how this affects the project?
A. It makes it easier to manage
B. It increases the project risk
C. It requires more people
D. It makes it more expensive
6.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
Your project management plan results in a project schedule that is too long. If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do?
A. Fast track the project
B. Level the resources
C. Crash the project
D. Perform Monte Carlo analysis
7.
MULTIPLE CHOICE QUESTION
45 sec • 5 pts
A project manager is in the middle of executing a very large construction project when he discovers the time needed to complete the project is longer than the time available. What is the BEST thing to do?
A. Cut product scope
B. Meet with management and tell them the required date cannot be met
C. Work overtime
D. Determine options for schedule compression and present management with his recommended option.
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Chapt 7

Quiz
•
1st Grade
14 questions
RMP - 6. MONITOR & CLOSE RISK

Quiz
•
1st Grade
15 questions
PMI SH - Support Organizational Change

Quiz
•
1st - 3rd Grade
10 questions
Day-05 Installation follow UP

Quiz
•
1st Grade
5 questions
PMI SH - Define Team Ground Rules

Quiz
•
1st Grade
10 questions
Pedagogic Games V

Quiz
•
1st Grade - Professio...
10 questions
Chapt4

Quiz
•
1st Grade
13 questions
PMI-SH Plan and Manage Quality of Products/deliverables

Quiz
•
1st Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade