1.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?

A. Critical path method

B. Flowchart

C. Precedence diagramming

D. Work breakdown structure

2.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Which of the following are GENERALLY illustrated BETTER by bar charts than network diagrams?

A. Logical relationships

B. Critical paths

C. Resource trade-offs

D. Progress or status

3.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

If the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity?

A. 1

B. 1.3

C. 6

D. 3

4.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Lag means:

A. The amount of time an activity can be delayed without delaying the project finish date

B. The amount of time an activity can be delayed without delaying the early start date of its successor

C. Waiting time

D. The product of a forward and backward pass

5.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

A project has three critical paths. Which of the following BEST describes how this affects the project?

A. It makes it easier to manage

B. It increases the project risk

C. It requires more people

D. It makes it more expensive

6.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Your project management plan results in a project schedule that is too long. If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do?

A. Fast track the project

B. Level the resources

C. Crash the project

D. Perform Monte Carlo analysis

7.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

A project manager is in the middle of executing a very large construction project when he discovers the time needed to complete the project is longer than the time available. What is the BEST thing to do?

A. Cut product scope

B. Meet with management and tell them the required date cannot be met

C. Work overtime

D. Determine options for schedule compression and present management with his recommended option.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?