06. Schedule Management

Authored by sudiyuwono wowo

Professional Development

1st - 3rd Grade

Used 16+ times

06. Schedule Management
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An agile team estimates and averages a cycle time of three days per story and there are 30 stories. How much time it would take to complete the project?

10 business days
90 business days
30 business days
None of the above

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The agile project team you are managing is responsive for developing one of the five different components of a complex enterprise solution. Your PMO representative tells you she’s concerned because your team is using a larger story point unit than the other four teams. What should you do?

Tell the PMO that this is the story point your team has chosen, and it doesn’t matter how large it is relative to the other teams
Ask your team lead to coordinate their story point metric with the other teams to ensure that the different components interface smoothly
Explain to the PMO that the size of each team’s story point doesn’t matter since this is just a theoretical concept, not a real-world metric
Show the PMO why your story point has to be larger, since your part of the solution has more complex requirements than the others

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A Scrum Master is conducting sprint retrospective meeting which is becoming contentious. Which of the following action might the Scrum master take to address team conflict?

Intervening at the first sign of conflict to avoid escalation and potentially damaged relationship

Intervening when heated discussion occur, and taking a break if needed to address individuals privately.

Addressing inappropriate behavior during the meeting to hold individual accountable to the team

Using authority as Scrum master to decide for the team when the discussion reachs an impasse

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are project manager for a construction project. The steering group asked you to accelerate the schedule to meet an imposed date. As agreed with the steering group, you are constructing the foundation for a building before completing all of the architectural drawings. This is an example of ….

Re-prioritizing
Crashing
Fast tracking
Leads and lags

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is in the middle of executing a large construction project when he discovers the time needed to complete the project is longer than the time available. What is the best thing to do?

Cut product scope
Work overtime
Meet with management, and tell them the required date cannot be met
Determine options for schedule compression, and present management with the recommended option

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A new project manager is walking you through the schedule she has created for her project. She asks you about the duration of a particular milestone, so she knows how to properly schedule it. What will you tell her about a milestone's duration?

It is shorter than the duration of the longest activity
It has no duration
It is shorter than the activity it represents
It is the same length as the activity it represents

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your sponsor and stakeholders have made it clear they wish to be kept informed on the project status. There are many aspects of the pro on which you will report, and you want to choose the most appropriate tool to use in each case. Which of the following are generally illustrated better by bar charts than network diagrams?

Logical relationships
Resource trade-offs
Critical paths
Progress or status

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?