    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Baseline can be set when the project have all the draft schedule, approved budget, and assigned resources.

True

False

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Project can be set when the project have all the draft schedule, approved budget, and assigned resources.

True

False

3.

FILL IN THE BLANKS QUESTION

1 min • 1 pt

(a)   is the approved plan that will be used as reference for measuring performance in a project.

4.

FILL IN THE BLANKS QUESTION

1 min • 1 pt

A Baseline is the approved plan that will be used as reference for measuring (a)   in a project.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It is necessary to create baseline copy before you enter actual data because it will overwrite original plan with updates.

True

False

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It isn't necessary to create baseline copy before you enter actual data because it will overwrite original plan with updates.

True

False

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

In the SET BASELINE dialog box, you can set baseline with which options in the FOR: section.

Entire project

Selected tasks

Selected resources

Selected Projects

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

Already have an account?