Odoo 15 Cert - Manufacturing - Test Sample + Exam

Odoo 15 Cert - Manufacturing - Test Sample + Exam

Professional Development

49 Qs

quiz-placeholder

Similar activities

MA (New Mock-4,  23)

MA (New Mock-4, 23)

Professional Development

46 Qs

Finopedia 2.0

Finopedia 2.0

Professional Development

45 Qs

FFH Quiz #3

FFH Quiz #3

Professional Development

46 Qs

FR-IAS 2,13,41,8,16, 20, 40,23 & Framework (2024)

FR-IAS 2,13,41,8,16, 20, 40,23 & Framework (2024)

Professional Development

48 Qs

SELASAR W2 July

SELASAR W2 July

Professional Development

50 Qs

Final Assessment

Final Assessment

Professional Development

45 Qs

Odoo Functional Training L2 Quiz

Odoo Functional Training L2 Quiz

Professional Development

45 Qs

PMP 380 mock questions - Chapter 2 (Process)

PMP 380 mock questions - Chapter 2 (Process)

Professional Development

50 Qs

Odoo 15 Cert - Manufacturing - Test Sample + Exam

Odoo 15 Cert - Manufacturing - Test Sample + Exam

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Tools US Team

Used 60+ times

FREE Resource

49 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What documents will be generated when you confirm a SO with a product that has a BOM of type "Kit"?

A manufacturing order to produce the kit and a delivery order

A manufacturing order for the final product and a child MO for the kit.

A delivery order with components of the kit

A delivery order with the final product (kits are used when purchasing)

Answer explanation

Kit BoM doesn't create any MO.

So that, when SO contains product that has a BoM Kit, a delivery order is create contains components of this BoM Kits

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

On which document is the OEE computed?

Work Order

Manufacturing Order

Work Center

Equipment

Answer explanation

OEE in a WorkCenter is computed by all work order in this work center and its must be done.3

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

How is the Mean Time to Repair (MTTR) calculated?

Total Down time in days / number of breakdowns

Total time in days / number of breakdowns

(Total time in days - Total Down Time) / number of breakdowns

Total time in days / (number of breakdowns - 1)

Answer explanation

Media Image

equipment.mttr = len(maintenance_request) and (mttr_days/len(maintenance_request)) or 0

close_date : Date the maintenance was finished.

request_date = Date requested for the maintenance to happen

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

When are forecasted quantities updated for components used in a MO?

When MO is created

When MO is confirmed

At validation of finished product

When MO is marked as Done

Answer explanation

- Forecasted Qty in a location is computed by Quantity On Hand (current stock) + Quantity Product in Transfer move to this location - Quantity Product in Transfer bring out from this location.  These transfer are planned.

- When MO is not confirmed. There are not any transfer is created. So when MO is confirmed. Transfers have just been created.

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

How would you setup a BOM to produce several finished products?

Use sub-bom (kits)

You can define extra products in the routing

Define byproducts on the BOM

Answer explanation

In Odoo, a by-product is any product produced by a BoM in addition to the primary product.

6

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What will be the text recorded in the productivity column if I go over the expected duration of my work order?

Fully Productive Time

Reduced Speed

2 lines: 1 for "Fully Productive Time" and 1 for "Reduced Speed"

1 line with both "Fully Productive Time" and "Reduced Speed"

Answer explanation

Media Image

For example : 1 min expected duration

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

In an OEE calculation, what's included in the "Fully Productive Time"?

All recorded time on a work order until it is marked as "Done"

All recorded time that doesn't exceed the expected working time.

All recorded time on the work order, during working schedule of work center

Answer explanation

productive = Fully Productive Time

OEE only calculate any work order has date end (done)

Fully Productive Time is WorkOrder has lime less than expected or equal to expected duration and must be done

So B is the answer.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?