What documents will be generated when you confirm a SO with a product that has a BOM of type "Kit"?
A manufacturing order to produce the kit and a delivery order
A manufacturing order for the final product and a child MO for the kit.
A delivery order with components of the kit
A delivery order with the final product (kits are used when purchasing)
Answer explanation
Kit BoM doesn't create any MO.
So that, when SO contains product that has a BoM Kit, a delivery order is create contains components of this BoM Kits
2.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
On which document is the OEE computed?
Work Order
Manufacturing Order
Work Center
Equipment
Answer explanation
OEE in a WorkCenter is computed by all work order in this work center and its must be done.3
3.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
How is the Mean Time to Repair (MTTR) calculated?
Total Down time in days / number of breakdowns
Total time in days / number of breakdowns
(Total time in days - Total Down Time) / number of breakdowns
Total time in days / (number of breakdowns - 1)
Answer explanation
equipment.mttr = len(maintenance_request) and (mttr_days/len(maintenance_request)) or 0
close_date : Date the maintenance was finished.
request_date = Date requested for the maintenance to happen
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
When are forecasted quantities updated for components used in a MO?
When MO is created
When MO is confirmed
At validation of finished product
When MO is marked as Done
Answer explanation
- Forecasted Qty in a location is computed by Quantity On Hand (current stock) + Quantity Product in Transfer move to this location - Quantity Product in Transfer bring out from this location. These transfer are planned.
- When MO is not confirmed. There are not any transfer is created. So when MO is confirmed. Transfers have just been created.
5.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
How would you setup a BOM to produce several finished products?
Use sub-bom (kits)
You can define extra products in the routing
Define byproducts on the BOM
Answer explanation
In Odoo, a by-product is any product produced by a BoM in addition to the primary product.
6
6.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What will be the text recorded in the productivity column if I go over the expected duration of my work order?
Fully Productive Time
Reduced Speed
2 lines: 1 for "Fully Productive Time" and 1 for "Reduced Speed"
1 line with both "Fully Productive Time" and "Reduced Speed"
Answer explanation
For example : 1 min expected duration
7.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
In an OEE calculation, what's included in the "Fully Productive Time"?
All recorded time on a work order until it is marked as "Done"
All recorded time that doesn't exceed the expected working time.
All recorded time on the work order, during working schedule of work center
Answer explanation
productive = Fully Productive Time
OEE only calculate any work order has date end (done)
Fully Productive Time is WorkOrder has lime less than expected or equal to expected duration and must be done
So B is the answer.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?