1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The purpose of initial verification is

to give the customer a certificate

to verify the installation is safe to use

to check the circuits work

to show competence

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The recommended maximum value for Main Earth Bonding is

3.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Single pole switches must be connected in the ? conductor?

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which sense can be used to locate a sharp trunking corner?

Taste

Smell

Touch

Sight

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When inspecting accessories it is important that

the CPC is appropriately identified

the screw heads are lined up

there is a minimum of cable inside

there is copper showing

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the UK electrical sockets and switches should be mounted

where the client wants them

where the sun sets at the Winter equinox

in accessible areas

as suggested by Appendix H OSG

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Insulation resistance should be performed with

an insulation resistance tester

a Fluke

a Megger

a multi-function tester

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?