1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A budget for 8,000 units of output shows direct materials cost of £17,400 and a direct labour cost of £12,600. Actual output is 9,000 units.

Using a flexed budget which is correct?

direct materials £19,575

direct labour £14,175

direct materials £19,575

direct labour £12,600

direct materials £17,400

direct labour £14,175

direct materials £17,400

direct labour £12,600

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a Fixed cost for a manufacturing business?

Raw materials to make the product

Salaries of maintenance staff

Production workers paid on the basis of work done

Royalties paid to the designer of the product

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

What is the Economic Order Quantity (EOQ) for material XX5?

£1200

144,000 kg

£144,000

1200 kg

Answer explanation

2x7200x20/£2

2880000/£2

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

A company pays its production-line employees on a piecework basis, but with a guaranteed rate. How much will R Williams be paid?

£400

£450

£435

£396

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

From the list below, what would be the best basis of apportionment for lighting and heating overheads?

Carrying value of production equipment

Number of employees

Factory floor space

Time spent servicing production equipment

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

What is the budgeted overhead absorption rate for each department if both are heavily automated?

Cutting £9, Assembly £25

Cutting £9, Assembly £75

Cutting £20, Assembly £25

Cutting £20, Assembly £75

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

What is the budgeted overhead absorption rate for each department if both are labour intensive?

Cutting £9, Assembly £25

Cutting £9, Assembly £75

Cutting £20, Assembly £25

Cutting £20, Assembly £75

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development