Project Scope Management

Project Scope Management

Professional Development

10 Qs

quiz-placeholder

Similar activities

Project Management (Week 4)

Project Management (Week 4)

Professional Development

8 Qs

Understand Project Scope Management

Understand Project Scope Management

Professional Development

7 Qs

Scope Management - Campus Biomedico

Scope Management - Campus Biomedico

Professional Development

5 Qs

Project Management Module

Project Management Module

Professional Development

10 Qs

PMP PROJECT QUALITY MANAGEMENT

PMP PROJECT QUALITY MANAGEMENT

Professional Development

10 Qs

Project Scope Management

Project Scope Management

Professional Development

15 Qs

CAPM 1 (10 Questions)

CAPM 1 (10 Questions)

Professional Development

10 Qs

PMP PROJECT COMMUNICATIONS MANAGEMENT

PMP PROJECT COMMUNICATIONS MANAGEMENT

Professional Development

10 Qs

Project Scope Management

Project Scope Management

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Michael Myers

Used 3+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

George is managing a construction project and currently sequencing the project activities and defining their logical relationships. Two activities have both the SS and FF relationships. How should George schedule these activities?

Apply both the relationships.

Select the relationship with the highest impact.

Select the SS relationship as this is more logical than the FF relationship.

Select the FF relationship as this can help meet the project deadlines.

Answer explanation

Multiple relationships between the same activities are not recommended, so a decision has to be made to select the relationship with the highest impact.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As part of tracking a project, a project manager is validating the completion of project scope. He or she would measure this against:

Requirements Traceability Matrix

The Project Management Plan

The Project Charter

The Requirements Management Plan

Answer explanation

Completion of project scope is measured against the scope baseline which is a part of the project management plan. In contrast, the product scope is measured against the product requirements.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following processes is not a part of the Project Scope Management?

Create WBS

Control Quality

Control Scope

Collect Requirements

Answer explanation

Control Quality is not a part of the Project Scope management.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Establishing control accounts for the work packages and a unique identifier from a code of accounts finalizes the WBS. This provides a structure for hierarchical summation of:

Schedule and requirements information

Cost and requirements information

Cost and resource information

Scope, budget and schedule information

Answer explanation

The WBS is finalized by establishing control accounts for the work packages and a unique identifier from a code of accounts. This provides a management control point for integrated scope, schedule and cost information.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Uncontrolled project scope changes are often referred to as ______________.

Scope Creep

Scope Verification

Value Added Scope

Scope Control

Answer explanation

Uncontrolled project scope changes are often referred to as scope creep. Scope creep is often viewed negatively, but can be managed using a change control process.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While managing a project, you have included the product acceptance criteria in the Quality Management Plan. While reviewing your plan, a senior manager asks you to reconsider this. You then realize that what you did is incorrect. Where should you place the product acceptance criteria?

Project Charter

Change Control Process

Project Scope Statement

Scope Verification Plan

Answer explanation

The project scope statement documents and addresses the characteristics and boundaries of the project and its associated products and services, as well as product acceptance criteria and scope control.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Project Scope Management Knowledge Area is primarily concerned with:

Defining the scope of work that included in the project

Ensuring that the project includes all the work required, and only the work

required, to complete the project

The scope of work required during the initiation phase

Defining the specifications and functionality of the work product

Answer explanation

Project Scope Management includes the processes required to ensure that the project includes all the work required and only the work required to complete the project successfully. It is primarily concerned with defining and controlling what is included and what is not included in the project.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?