REMEDIAL 2024

REMEDIAL 2024

University

40 Qs

quiz-placeholder

Similar activities

Seismic survey+, Prepositions AT - IN - ON

Seismic survey+, Prepositions AT - IN - ON

6th Grade - University

39 Qs

1 Part - ERP/By @Kazima

1 Part - ERP/By @Kazima

University

37 Qs

Principles of management

Principles of management

University

36 Qs

RIASEC Work Quiz

RIASEC Work Quiz

9th Grade - University

39 Qs

Executive Functioning

Executive Functioning

KG - University

37 Qs

Practice Test 2 - Part 2

Practice Test 2 - Part 2

University

35 Qs

2024-25-2S-PROF4-MQ1

2024-25-2S-PROF4-MQ1

University

35 Qs

POBF 2.02 Review

POBF 2.02 Review

9th Grade - University

45 Qs

REMEDIAL 2024

REMEDIAL 2024

Assessment

Quiz

Other

University

Hard

Created by

Achmad MPM.

Used 1+ times

FREE Resource

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A form of project organization where power is shared between the functional manager and the project manager is called:
A week matrix
A balanced matrix
A strong matrix
A tight matrix

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91. Generally, what is the BEST explanation for why this occurred?
The scope was changed.
A supplier went out of business and a new one needed to be found.
Additional equipment needed to be purchased.
A critical path activity took longer and needed more labor hours to complete.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project is in planning when three stakeholders come to the project manager asking for information on the company’s new project management methodology. They want to know where it came from and why is it different from the way they currently manage projects. These stakeholders are also friends of the project manager and the entire group has worked together for years. The project is using new terms like “corrective action” that are making some stakeholders nervous, as they are unsure whether the way the project will be managed is going to change along with new terms. What should the project manager do..?
Notify the Project Management Office (PMO)
Make sure she maintains her authority as the project manager even the stakeholders are her friends
Supply a list of new terms and their terminology
Advise the stakeholders that she will keep them in the communication loop for the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager analyzed a US $2,500,000 project that involves 75 team members and has three customers. Why is there a need for an analysis of secondary risks on this project..?
It helps create prioritized list of risks
It provides a way to effectively decrease the amount of contracting on the project.
It helps determine and address new risks created as result of the risk response strategies chosen
It provides a vehicle for efficient stakeholder involvement.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An activity has an Early Start (ES) of day 3, a Late Start (LS) of day 13, an Early Finish (EF) of day 9, a Late Finish (LF) of day 19. What is the duration of this activity..?
7
10
6
12

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

People from business development department are the only ones completing a project. Whenever questions arise, they are transmitted to the heads of other department, to the people in these departments and the back to the business development department. This is causing delays on the project. Why might this method of communicating be happening?
There is no project charter
The communication management plan is not clear
The work break down structures does not show responsibilities
The project is being managed in functional organization.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It is determined that the benefit of the internal ticket tracking system will be in the range of US $150,000 to US $230,000. The overall cost of the project is approximately US $250,000. Team members could learn new skills and their staff would benefit from its use. Which of the following tools could be used by management to determine whether this project should be done..?
Design of experiments
Cost of quality
Cost-benefit analysis
Statistical sampling

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?