
2-1 Resource Management

Quiz
•
Architecture
•
University
•
Hard

Centari Rodriguez
Used 1+ times
FREE Resource
9 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
An architect at a firm with in-house MEP design services pursues an RFP for a design-build refrigerated warehouse project with an aggressive schedule.
Which of the following consultants or partners will need to be contracted by the architect's firm? Check the three that apply.
General contractor
Food service consultant
Refrigeration consultant
Electrical engineer
Structural engineer
2.
FILL IN THE BLANK QUESTION
1 min • 1 pt
An architect planned 1,000 hours for the design development (DD) phase of a project with an average billing rate of $50 per hour. The project has a planned multiplier of 3.05 and a total DD phase compensation of $152,500. At the end of DD, the architect finds that an excess of 240 labor hours were needed for DD.
What is the additional project cost?
3.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
A university hires an architect to design a renovation and addition to a performing arts center. The university wants to use an integrated project delivery method and contract with a series of consultants who will each coordinate their scope of work with the architect. The work is to be executed in multiple phases and includes the following:
Restore the original facade of the existing facility built in 1905.
Convert the existing sloped concrete floor performance hall into a new flat floor performance space.
Renovate existing classrooms to provide new advanced audio and video laboratories.
Design a performance hall addition connected to the existing facility by an elevated walkway.
Identify and address any AHJ or accessibility issues in the existing facility.
Who should the architect recommend the university hire before the schematic design phase? Check the four that apply.
General contractor
Geotechnical engineer
Commissioning agent
Historical preservationist
Construction manager
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
An architect is responding to an RFP for a ground-up research laboratory located on a wetland site. The site includes new road access and must be designed to meet local codes and ordinances.
Which of the following subconsultants should the architect include on their project team? Check the four that apply.
Environmental engineer
MEP engineer
Civil engineer
Landscape architect
Site surveyor
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect is working under AIA B101 for a project. The terms of the agreement state that compensation is to be calculated as 6% of the owner’s $17,500,000 budget for the cost of the work. The compensation for the architect’s basic services are as follows:
Schematic Design: 10%
Design Development: 20%
Construction Documents: 30%
Procurement: 10%
Construction: 30%
Prior to completing construction documents, the owner requests changes that increase the cost of work by 2%.
How much compensation will the architect receive for the construction documents phase?
$315,000
$321,300
$630,000
$636,300
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect is preparing an initial project budget using the following fee information:
There is a total fee of $300,000 for the entire project team.
40% of the total fee is allocated for all consultants.
8% of the net fee is allocated for the architect's non-reimbursable expenses.
7% of the net fee is allocated for the architect's contingency.
What is the available budget for project labor?
$153,000
$165,000
$180,000
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
An owner is assembling a project team for the conceptual design phase of an eight-story, greenfield office building development that will include underground parking.
Which team members should the architect recommend be required for this project team? Check the four that apply.
Architect
MEP engineers
Structural engineer
Geotechnical engineer
Landscape architect
8.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
An owner wants to build a warehouse and has hired the architect to develop a building program and document the owner's requirements. The programming documents have just been completed.
Which delivery method should the architect suggest to minimize the need for owner involvement in finishing the project?
Design-bid-build
Design-build
CM at-risk
Integrated project delivery
9.
FILL IN THE BLANK QUESTION
1 min • 1 pt
Refer to the exhibit.
An architect determines that construction documents are now 50% complete. The total amount invoiced to the owner up to this point is $94,000.
How much profit has the firm currently earned from this project?
Similar Resources on Wayground
10 questions
Introduction to CAD

Quiz
•
7th Grade - University
9 questions
Interior Architecture Quiz

Quiz
•
University
9 questions
MODA 5.1 VIDEO Construction of the Bellas Artes palace

Quiz
•
University
10 questions
SITE VISIT QUIZ

Quiz
•
University
10 questions
4) Building Economics and certificates

Quiz
•
University
13 questions
3-3 Administrative Procedures & Protocols

Quiz
•
University
10 questions
LAN100 Principle of Design

Quiz
•
University
11 questions
Masters of Architecture Quiz

Quiz
•
University
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade
Discover more resources for Architecture
10 questions
Would you rather...

Quiz
•
KG - University
20 questions
Definite and Indefinite Articles in Spanish (Avancemos)

Quiz
•
8th Grade - University
7 questions
Force and Motion

Interactive video
•
4th Grade - University
10 questions
The Constitution, the Articles, and Federalism Crash Course US History

Interactive video
•
11th Grade - University
7 questions
Figurative Language: Idioms, Similes, and Metaphors

Interactive video
•
4th Grade - University
20 questions
Levels of Measurements

Quiz
•
11th Grade - University
16 questions
Water Modeling Activity

Lesson
•
11th Grade - University
10 questions
ACT English prep

Quiz
•
9th Grade - University