2-3 Contracts

2-3 Contracts

University

14 Qs

quiz-placeholder

Similar activities

OFFICE PROJECT MANAGEMENT

OFFICE PROJECT MANAGEMENT

University

11 Qs

PP - RA 9266

PP - RA 9266

University

12 Qs

Construction Drawings 15

Construction Drawings 15

9th Grade - University

10 Qs

Formwork, Col & Slabs Quiz

Formwork, Col & Slabs Quiz

University

15 Qs

Professional Practice Quiz#2

Professional Practice Quiz#2

University

10 Qs

Project Delivery

Project Delivery

University

18 Qs

W: SET 2

W: SET 2

University

10 Qs

Building Laws Quiz 1- PD 1096

Building Laws Quiz 1- PD 1096

KG - Professional Development

15 Qs

2-3 Contracts

2-3 Contracts

Assessment

Quiz

Architecture

University

Medium

Created by

Centari Rodriguez

Used 1+ times

FREE Resource

14 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An architect is designing a new apartment building. The owner has a separate contract with the structural engineer. After the 100% CD set is issued to the contractor for construction, the structural engineer increases the floor beam size due to a miscalculation of the seismic load. As a result, the plumbing engineer needs to reroute the sanitary stack and the architect must redesign the bathroom layouts to accommodate a new chase.

What should the architect do first?

Incorporate the changes into the drawings and issue a revision to the contractor.

Revise the drawings and send an invoice to the structural engineer for additional design fee due to their errors. 

Submit an additional service request to the owner for approval prior to incorporating changes into the drawings.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Using an AIA C401, an architect contracts with a subconsultant to help build the strategic plan and vision for a new airport project. The subconsultant is another architect who has airport and aviation industry expertise. When will the subconsultant receive their first payment?

Schematic Design

Design Development

Construction Documents

Construction Administration

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Working under an AIA B101, an architect is hired by an owner to renovate an existing performing arts center. A design-bid-build delivery method will be used. The owner has contracts with an advising construction manager and a series of consultants who each coordinate their scope of work with the architect.

Instead of the agreed-upon 21 days, the owner's theatrical lighting consultant sends updated drawings to the architect for final coordination 14 days prior to completing the construction documents. The consultant's updated drawings show significantly more lighting equipment and materials than the previous coordination drawings. The start of bidding cannot be delayed.

What should the architecture firm do first after receiving the updated drawings?  

Send the owner a request for compensation for additional coordination services.

Instruct the electrical engineer to prioritize the coordination of the new lighting drawings.

Ask the construction manager to update the theatrical lighting submittals.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An architect is executing a field survey for the renovation of an existing facility constructed in 1962 and unmodified since 1987. The architect observes what appears to be utility piping insulation that is original to the building.

How should the architect address this observation?

Alert the local building official of the potential hazardous materials.

Advise the owner to engage a third-party hazardous materials testing consultant.

Direct the plumbing consultant to include potential hazardous materials abatement in their bid drawings.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An architect has designed a project that the owner needs to be operational before the end of the year. As the bid package is being put together, the owner asks the architect for the most appropriate method of ensuring that the selected contractor meets the deadline. The owner is committed to not changing the design during construction. 

Which one of the following should the architect recommend?

Provide a contract provision for consequential damages to complete unfinished work.

Provide a budget contingency for unforeseen schedule impacts.

Provide a contract provision for liquidated damages.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An architect hires an electrical engineer using AIA C401. The electrical engineer, in turn, hires a specialty subconsultant. Review comments from the AHJ note that there are significant electrical code oversights that need to be addressed. The architect must inform the owner that these revisions will cause a delay in the overall project schedule.

Who is responsible to the owner for the delay in the project schedule?

The architect

The electrical engineer

The specialty subconsultant

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An architect is working on a large project with a construction manager (CM) as-contractor. All designers and engineers have been retained and the design is approximately 50% complete. Due to the size of the project, the CM is unable to secure a bond for the entire contracted project. Smaller construction contracts will be necessary. The owner and architect want all design and construction team members to continue in their current roles.

Which delivery method should the architect recommend to the owner?

Design-build

CM as-advisor

Multiple prime

Design-bid-build

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?