
2-3 Contracts

Quiz
•
Architecture
•
University
•
Medium

Centari Rodriguez
Used 1+ times
FREE Resource
14 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect is designing a new apartment building. The owner has a separate contract with the structural engineer. After the 100% CD set is issued to the contractor for construction, the structural engineer increases the floor beam size due to a miscalculation of the seismic load. As a result, the plumbing engineer needs to reroute the sanitary stack and the architect must redesign the bathroom layouts to accommodate a new chase.
What should the architect do first?
Incorporate the changes into the drawings and issue a revision to the contractor.
Revise the drawings and send an invoice to the structural engineer for additional design fee due to their errors.
Submit an additional service request to the owner for approval prior to incorporating changes into the drawings.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Using an AIA C401, an architect contracts with a subconsultant to help build the strategic plan and vision for a new airport project. The subconsultant is another architect who has airport and aviation industry expertise. When will the subconsultant receive their first payment?
Schematic Design
Design Development
Construction Documents
Construction Administration
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Working under an AIA B101, an architect is hired by an owner to renovate an existing performing arts center. A design-bid-build delivery method will be used. The owner has contracts with an advising construction manager and a series of consultants who each coordinate their scope of work with the architect.
Instead of the agreed-upon 21 days, the owner's theatrical lighting consultant sends updated drawings to the architect for final coordination 14 days prior to completing the construction documents. The consultant's updated drawings show significantly more lighting equipment and materials than the previous coordination drawings. The start of bidding cannot be delayed.
What should the architecture firm do first after receiving the updated drawings?
Send the owner a request for compensation for additional coordination services.
Instruct the electrical engineer to prioritize the coordination of the new lighting drawings.
Ask the construction manager to update the theatrical lighting submittals.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect is executing a field survey for the renovation of an existing facility constructed in 1962 and unmodified since 1987. The architect observes what appears to be utility piping insulation that is original to the building.
How should the architect address this observation?
Alert the local building official of the potential hazardous materials.
Advise the owner to engage a third-party hazardous materials testing consultant.
Direct the plumbing consultant to include potential hazardous materials abatement in their bid drawings.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect has designed a project that the owner needs to be operational before the end of the year. As the bid package is being put together, the owner asks the architect for the most appropriate method of ensuring that the selected contractor meets the deadline. The owner is committed to not changing the design during construction.
Which one of the following should the architect recommend?
Provide a contract provision for consequential damages to complete unfinished work.
Provide a budget contingency for unforeseen schedule impacts.
Provide a contract provision for liquidated damages.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect hires an electrical engineer using AIA C401. The electrical engineer, in turn, hires a specialty subconsultant. Review comments from the AHJ note that there are significant electrical code oversights that need to be addressed. The architect must inform the owner that these revisions will cause a delay in the overall project schedule.
Who is responsible to the owner for the delay in the project schedule?
The architect
The electrical engineer
The specialty subconsultant
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An architect is working on a large project with a construction manager (CM) as-contractor. All designers and engineers have been retained and the design is approximately 50% complete. Due to the size of the project, the CM is unable to secure a bond for the entire contracted project. Smaller construction contracts will be necessary. The owner and architect want all design and construction team members to continue in their current roles.
Which delivery method should the architect recommend to the owner?
Design-build
CM as-advisor
Multiple prime
Design-bid-build
Create a free account and access millions of resources
Similar Resources on Wayground
11 questions
Introduction to Urban Design

Quiz
•
University
9 questions
2-1 Resource Management

Quiz
•
University
11 questions
S4.1 Return Brief & Fee Proposal

Quiz
•
University
15 questions
Our Professional Avenues

Quiz
•
University
10 questions
Construction Management Services Quiz

Quiz
•
University
10 questions
Construction management : Finances

Quiz
•
University
10 questions
Key Players in Construction

Quiz
•
University
15 questions
S26 Service

Quiz
•
University
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade