Five new Scrum Teams have been created to build one product. A few of the developers on one of the Developers ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?
Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.
Teach them that it is their responsibility to work with the other teams to create an integrated Increment.
Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
Visit the five teams each day to inspect that their Sprint Backlogs are aligned.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who must attend the Daily Scrum?
The Scrum Master and Product Owner
The Developers
The Developers and Product Owner.
The Scrum team
The Developers and Scrum Master.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the key concern when multiple Developers are working from the same Product Backlog?
Minimizing dependencies between teams
Clear definition of requirements
Meeting original scope projection
Making sure there’s enough work for everyone on every team.
Maximizing velocity
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which outcome is expected as Scrum Teams mature?
They will improve their definition of “Done” to include more stringent criteria
The Sprint Retrospectives will grow to be longer than 4 hours.
There is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.
Sprint Reviews will no longer be needed
A Scrum Master is no longer needed since they are a mature team now.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A properly functioning Scrum Team will have at least one Release Sprint and may well have several.
True
False
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A Developer asks their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a specific software component. Without that component there won’t be enough work in the next Sprint to occupy the full team. The Product Owner asks the Scrum Master for help. What would be good advice to give the Product Owner?
Remind the Product Owner that his primary concern is the flow of value reflected in the ordering of the Product Backlog
Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate sprint.
Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Developer
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
When the Product Owner identifies new work
As soon as possible after they are identified
When the Scrum Master has time to enter them
During the Daily Scrum after the Developer approves them
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?