Find the project completion time for this project.
5 weeks
11 weeks
8 weeks
12 weeks
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Find the critical path for this project.
B - C - F - E
B - C - E - F
B - F - E - C
B - E - C - F
3.
FILL IN THE BLANK QUESTION
2 mins • 1 pt
How many priority rules that you have learned?
(a)
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Find the optimal solution work centre 1 and work centre 2 for Johnsons rule.
B - E - C - D - A
B - E - D - C - A
B - A - C - D - E
B - E - D - A - C
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which item is NOT considered component in MRP?
Projected on hand
Planned order releases
Phantom bill
Net material requirement
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Given data below, calculate UCLc. (z = 1.96)
12.19
2.35
20.72
1.81
7.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Bujang Lapok Sdn Bhd. uses 5000 units of item XYZ per year. It costs the company RM50 per order of the item and RM2 per unit per year to keep the item in stock.
Based on the above information, determine the Total Annual Inventory Costs.
RM100
RM500
RM1000
RM5000
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?