CMA 490 - Chapter 2 Review

CMA 490 - Chapter 2 Review

University

18 Qs

quiz-placeholder

Similar activities

HOA - Pre Historic

HOA - Pre Historic

University

20 Qs

Architecture and Design Quiz

Architecture and Design Quiz

University

13 Qs

What do you know about Carnival?

What do you know about Carnival?

8th Grade - University

18 Qs

BLDG LAWS BP344

BLDG LAWS BP344

University

15 Qs

Park Planning and Design

Park Planning and Design

University

18 Qs

Roof Structures

Roof Structures

University

20 Qs

Location, Inspiration, Brand Innovation: Warmup

Location, Inspiration, Brand Innovation: Warmup

University

14 Qs

JEE Paper-2 Mock Test 1

JEE Paper-2 Mock Test 1

7th Grade - Professional Development

20 Qs

CMA 490 - Chapter 2 Review

CMA 490 - Chapter 2 Review

Assessment

Quiz

Architecture

University

Easy

Created by

Jeremiah Arnett

Used 47+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

18 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A ___ is a hierarchically structured system of tasks that represent the workflow of a construction project in increasing levels of detail.

project detail

construction contract

work breakdown structure

workflow process

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project ___ is a description of a project being built, the major tasks and their deliverables, and any milestones, deadlines, or exclusions.

scope

contract

detail

orientation

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The advantage of the bottom-up approach to developing a schedule is that ___.

it is short and concise

it avoids scope gaps

smaller activities can be left out

individual tasks can be laid out quickly from start to finish

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

One advantage of the ___ approach is that it helps to divide complex projects into different areas of work that can then be broken down into detail.

bottom-up

top-down

historical

phased

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

At the highest level of a work breakdown structure is the ___.

project itself

activity

project phase

work package

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A(n) ___ is the lowest level in a work breakdown structure and has a grouping of tasks below it.

substructure

activity

construction phase

work package

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An activity is usually ___ days or less in duration and encompasses a single subcontractor, individual, or resource.

3

7

10

15

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?