CMA 490 - Chapter 2 Review

CMA 490 - Chapter 2 Review

University

18 Qs

quiz-placeholder

Similar activities

Project Delivery

Project Delivery

University

18 Qs

Construction Technology

Construction Technology

University

20 Qs

Building Information Modelling Quiz

Building Information Modelling Quiz

University

14 Qs

PRO PRAC MOD- 2

PRO PRAC MOD- 2

University

22 Qs

Business Interior Design

Business Interior Design

University

17 Qs

LANDFILL LECTURE 5

LANDFILL LECTURE 5

University

20 Qs

PROFESSIONAL PRACTICE 3 - MODULE 1 (ARCHITECTURAL FIRM)

PROFESSIONAL PRACTICE 3 - MODULE 1 (ARCHITECTURAL FIRM)

University

15 Qs

TOA_part 2

TOA_part 2

University

20 Qs

CMA 490 - Chapter 2 Review

CMA 490 - Chapter 2 Review

Assessment

Quiz

Architecture

University

Medium

Created by

Jeremiah Arnett

Used 46+ times

FREE Resource

18 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A ___ is a hierarchically structured system of tasks that represent the workflow of a construction project in increasing levels of detail.

project detail

construction contract

work breakdown structure

workflow process

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project ___ is a description of a project being built, the major tasks and their deliverables, and any milestones, deadlines, or exclusions.

scope

contract

detail

orientation

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The advantage of the bottom-up approach to developing a schedule is that ___.

it is short and concise

it avoids scope gaps

smaller activities can be left out

individual tasks can be laid out quickly from start to finish

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

One advantage of the ___ approach is that it helps to divide complex projects into different areas of work that can then be broken down into detail.

bottom-up

top-down

historical

phased

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

At the highest level of a work breakdown structure is the ___.

project itself

activity

project phase

work package

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A(n) ___ is the lowest level in a work breakdown structure and has a grouping of tasks below it.

substructure

activity

construction phase

work package

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An activity is usually ___ days or less in duration and encompasses a single subcontractor, individual, or resource.

3

7

10

15

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?

Discover more resources for Architecture