Quiz PMO session3 (Scope)

Quiz PMO session3 (Scope)

1st Grade

10 Qs

quiz-placeholder

Similar activities

Growth Mindset or Fixed Mindset?_P123

Growth Mindset or Fixed Mindset?_P123

1st - 3rd Grade

7 Qs

My Body Parts

My Body Parts

1st - 3rd Grade

15 Qs

Self-management

Self-management

1st - 3rd Grade

10 Qs

Dogs

Dogs

KG - 8th Grade

10 Qs

Logo Bash-Dash!

Logo Bash-Dash!

KG - Professional Development

11 Qs

Guidelines in Airclass

Guidelines in Airclass

1st Grade

10 Qs

FIFA 21

FIFA 21

1st - 3rd Grade

12 Qs

Animal in the artic

Animal in the artic

1st - 2nd Grade

13 Qs

Quiz PMO session3 (Scope)

Quiz PMO session3 (Scope)

Assessment

Quiz

Other

1st Grade

Practice Problem

Hard

Created by

Misbahuddin Misbahuddin

Used 3+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

1.       Triple Constraint for Scope in Waterfall and Agile can be described as follows:

a. Waterfall Scope is Fixed, Agile Scope is Fixed also

b. Waterfall Scope is Fixed, Agile Scope is Variable

c. Waterfall Scope is Variable, Agile Scope is Fixed

d. Waterfall Scope is Variable, Agile Scope is Variable also

Answer explanation

Scope: Waterfall (fixed), Agile (Variable)

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

2. During which part of the project management "process" is the "Work Breakdown Structure" created?

Initiating

Planning

Execution

Control & Monitoring

Answer explanation

Planning process

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

3. Which tool and technique is used in the processes Create WBS and Define activities?

a. Nominal group technique

b. Human resource assignment

c. Variance analysis

d. Decomposition

Answer explanation

WBS use Decomposition

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

4. Below is the benefit of Creating WBS for the Project, EXCEPT:

a. To show interdependency among the project scope

b. Communication & Information among Stakeholders

c. To avoid change & to avoid overlooked

d. As a reference to request the Resources

Answer explanation

WBS has not shown interdependency among the scope

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

5. Validate scope is closely related to :

a. Quality Control

b. Sequence Activities

C.  Manage Quality

d. Schedule management

Answer explanation

Control Quality

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

6. Which of the following is an output of the “Collect Requirements Process”?

a. Project scope statement

b. Work breakdown structure

c. Change Request

d. Requirement traceability matrix

Answer explanation

Requirement Traceability Matrix

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

7. As a PM you just completed sign-off on the scope statement for your new project. A key stakeholder has informed you that a deliverable is missing from the scope statement. This deliverable is critical for the project's success. Which of the following action should you take?

A. Inform the stakeholder that work not stated in scope statement is excluded from the project.

B. Modify the scope statement to reflect the new deliverable

C. Inform the stakeholder that this deliverable can be included in the next project since the sign-off has already been obtained

D. Modify the scope statement after an approved change request has been received from the stakeholder.

Answer explanation

D. Modify the scope statement after an approved change request has been received from the stakeholder.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?