1.

MULTIPLE CHOICE

1 min • 1 pt

1.       Triple Constraint for Scope in Waterfall and Agile can be described as follows:

Answer explanation

Scope: Waterfall (fixed), Agile (Variable)

2.

MULTIPLE CHOICE

1 min • 1 pt

2. During which part of the project management "process" is the "Work Breakdown Structure" created?

Answer explanation

Planning process

3.

MULTIPLE CHOICE

1 min • 1 pt

3. Which tool and technique is used in the processes Create WBS and Define activities?

Answer explanation

WBS use Decomposition

4.

MULTIPLE CHOICE

1 min • 1 pt

4. Below is the benefit of Creating WBS for the Project, EXCEPT:

Answer explanation

WBS has not shown interdependency among the scope

5.

MULTIPLE CHOICE

1 min • 1 pt

5. Validate scope is closely related to :

Answer explanation

Control Quality

6.

MULTIPLE CHOICE

1 min • 1 pt

6. Which of the following is an output of the “Collect Requirements Process”?

Answer explanation

Requirement Traceability Matrix

7.

MULTIPLE CHOICE

1 min • 1 pt

7. As a PM you just completed sign-off on the scope statement for your new project. A key stakeholder has informed you that a deliverable is missing from the scope statement. This deliverable is critical for the project's success. Which of the following action should you take?

Answer explanation

D. Modify the scope statement after an approved change request has been received from the stakeholder.

8.

MULTIPLE CHOICE

1 min • 1 pt

8.  When should scope validation be done?

Answer explanation

C. At the end of each phase of the project

9.

MULTIPLE CHOICE

1 min • 1 pt

9. What is the Scope Creeps and Gold Plating in project scope management:

Answer explanation

d.       Gold Plating is adding extra features that were not part of the original scope, while Scope Creeps is uncontrolled changes or expansions to project scope without adjusting the project’s time, cost, or other resources

10.

MULTIPLE CHOICE

1 min • 1 pt

10. Control Scope is under which process group

Answer explanation

Control Scope is a process of Controlling & Monitoring