PRM chapter 4

PRM chapter 4

University

48 Qs

quiz-placeholder

Similar activities

IT8075 - SPM - IAT2

IT8075 - SPM - IAT2

University

50 Qs

SPM VI

SPM VI

University

50 Qs

SPM REVISION I

SPM REVISION I

University

50 Qs

Basic Software Engineering

Basic Software Engineering

University

50 Qs

FullStack Django - [26 Apr 24] TEST - 2

FullStack Django - [26 Apr 24] TEST - 2

University

45 Qs

IT in Business Mid Term Test

IT in Business Mid Term Test

University

50 Qs

Sistem Informasi Manajemen

Sistem Informasi Manajemen

University

50 Qs

DC6- Multimedia Project

DC6- Multimedia Project

University

45 Qs

PRM chapter 4

PRM chapter 4

Assessment

Quiz

Computers

University

Easy

Created by

Hiếu Vũ

Used 9+ times

FREE Resource

48 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Integrated change control involves coordinating changes across the entire project.

T

F

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project integration management depends on activities from only five of the eight other knowledge areas.

T

F

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project integration management includes interface management.

T

F

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project integration management must occur within the context of a particular project, not the entire organization.

T

F

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project plans should be dynamic, flexible, and subject to change.

T

F

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A stakeholder analysis should be part of the overall project plan.

T

F

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project integration management views project planning and execution as intertwined and inseparable activities.

T

F

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?