EXTRA 2 - ADDITIONAL REVIEWER
Authored by REGGIE ALABA
Architecture
Professional Development
Used 20+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
100 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Removal of forms for footings.
1day
2days
3days
4days
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Removal of forms for columns.
1day
2days
3days
4days
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Removal of forms for slabs.
5day
2days
3days
4days
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Removal of forms side of beams.
3days
2days
1day
4days
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Removal of forms bottom of beams.
7days
12days
14days
10days
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Parking requirements for Hotel
1 slot/10 rooms
1 slot/40 rooms
1 slot/30 rooms
1 slot/20 rooms
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Parking requirements for Shopping center
1 slot/100m²
1 slot/50m²
1 slot/200m²
1 slot/300m²
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?