Scrum Planning and Estimation

Scrum Planning and Estimation

Professional Development

7 Qs

quiz-placeholder

Similar activities

Scrum Exp vs Real

Scrum Exp vs Real

Professional Development

5 Qs

SE_1

SE_1

Professional Development

10 Qs

Cuestionario - Agilidad

Cuestionario - Agilidad

Professional Development

10 Qs

Scrum

Scrum

University - Professional Development

10 Qs

Ch 4 Tp 1

Ch 4 Tp 1

Professional Development

8 Qs

Daily Scrum

Daily Scrum

10th Grade - Professional Development

10 Qs

Software Development methodologies

Software Development methodologies

11th Grade - Professional Development

10 Qs

Agile Methodology

Agile Methodology

KG - Professional Development

10 Qs

Scrum Planning and Estimation

Scrum Planning and Estimation

Assessment

Quiz

Computers

Professional Development

Medium

Created by

Hartono Kurniawan

Used 3+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What is the purpose of the Sprint Planning meeting in Scrum?

To review the progress of the current Sprint

To plan and select items from the Product Backlog for the upcoming Sprint

To prioritize items in the Product Backlog

To retrospect on the previous Sprint

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for creating the Product Backlog in Scrum?

The Scrum Master

The Development Team

The Product Owner

The stakeholders

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the recommended duration for a Sprint in Scrum?

1 week

2 weeks

3 weeks

4 weeks

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for estimating the effort required to complete each Product Backlog item?

The Scrum Master

The Development Team

The Product Owner

The stakeholders

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the Sprint Review meeting in Scrum?

To review the progress of the current Sprint

To plan and select items from the Product Backlog for the upcoming Sprint

To retrospect on the previous Sprint

To demonstrate and get feedback on the completed work in the current Sprint

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the Sprint Retrospective meeting in Scrum?

To review the progress of the current Sprint

To plan and select items from the Product Backlog for the upcoming Sprint

To retrospect on the previous Sprint

o demonstrate and get feedback on the completed work in the current Sprint

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main advantage of using Planning Poker for estimation in Scrum?

It provides a more accurate estimate

It saves time

It is easier to use than other estimation techniques

It is more fun than other estimation techniques