IWM507_2023_Test

IWM507_2023_Test

University

65 Qs

quiz-placeholder

Similar activities

HPC 107 FIRST GRADING EXAM

HPC 107 FIRST GRADING EXAM

University

60 Qs

PHARMACOLOGY FINALS PART 1

PHARMACOLOGY FINALS PART 1

University

70 Qs

OBSTRUCTIVE DISORDERS OF THE AIRWAY

OBSTRUCTIVE DISORDERS OF THE AIRWAY

University

69 Qs

Chiến lược tổ chức

Chiến lược tổ chức

University

60 Qs

Review unit 6  Part-2

Review unit 6 Part-2

University

63 Qs

Fundamentals of Marketing

Fundamentals of Marketing

University

60 Qs

THC 105 FIRST GRADING EXAM

THC 105 FIRST GRADING EXAM

University

65 Qs

Disorders of Children and Adolescents

Disorders of Children and Adolescents

University

69 Qs

IWM507_2023_Test

IWM507_2023_Test

Assessment

Quiz

Specialty

University

Medium

Created by

Berverly Nyakutsikwa

Used 1+ times

FREE Resource

65 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Which is the BEST definition to describe the work package?
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.
The work defined at the lowest level of the work breakdown structure for which cost and duration are estimated and managed.
A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and validated.
The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results .

2.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Generally, a bid differs from a proposal in that the term :
Bid is used when the seller selection decision will be based on price.
Bid is used when technical capability or technical approach are paramount.
Proposal is used when the selection decision will be based on price.
Proposal is used when the project time frame is limited.

3.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What is a work breakdown structure (WBS)?
A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results.
The sum of the products, services, and results to be provided as a project.
A contract between a service provider (either internal or external) and the end user that defines the level of service expected from the service provider .

4.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Select the answer that BEST describes test and evaluation documents :
Determining the appropriate combination of processes, inputs, tools, techniques, outputs, and life cycle phases to manage a project.
A dependent activity that logically comes after another activity in a schedule.
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables.
Project documents that describe the activities used to determine if the product meets thequality objectives stated in the quality management plan .

5.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

How would you define the statement of work (SOW)?
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.
A narrative description of products, services, or results to be delivered by the project.
The approved version of a scope statement, work breakdown structure (WBS), and itsassociated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results.
Formal responses from sellers to a request for proposal or other procurement document specifying the price, commercial terms of sale, and technical specifications or capabilities the seller will do for the requesting organization that, if accepted, would bind the seller to perform the resulting agreement.

6.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What is the BEST description for scope baseline ?
A component of the program or project management plan that describes how the scope will be defined, developed, monitored, controlled, .and validated.
The sum of the products, services, and results to be provided as a project.
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.
The approved version of a scope statement, work breakdown structure (WBS), and its associated WT3S dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results.

7.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What is the definition of cost baseline ?
A financial analysis tool used to determine the benefits provided by a project against its costs.
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost .

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?