CAPM Sample Exam

CAPM Sample Exam

Professional Development

30 Qs

quiz-placeholder

Similar activities

Naruto Quiz

Naruto Quiz

KG - Professional Development

25 Qs

C3 (Cerdas Cermat Cepat) Challenge - HD 2021

C3 (Cerdas Cermat Cepat) Challenge - HD 2021

Professional Development

35 Qs

Sports Quiz - Cognita

Sports Quiz - Cognita

7th Grade - Professional Development

25 Qs

FA Cup Quiz

FA Cup Quiz

KG - Professional Development

27 Qs

New Super Mario Bros. Wii Development [AI Generated]

New Super Mario Bros. Wii Development [AI Generated]

Professional Development

30 Qs

Rugby Logos

Rugby Logos

KG - Professional Development

25 Qs

Nfl teams

Nfl teams

2nd Grade - Professional Development

34 Qs

ACT_SW22_Agile

ACT_SW22_Agile

Professional Development

25 Qs

CAPM Sample Exam

CAPM Sample Exam

Assessment

Quiz

Fun

Professional Development

Easy

Created by

Anna Doueihi

Used 4+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

For a decision tree analysis, the cost of executing a decision is $50,000. For the benefit part, there is 40% chance that the decision provides a return of $90,000 and 60% chance that the decision provides a return of $30,000. What is the expected monetary value for this decision?

4,000$

28,000$

22,000$

12,000$

Answer explanation

EMV=[0.4x(90000-50000)]+[0.6x(30000-50000)]=4000 Since the EMV is positive, the decision can be taken

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your current project phase has 8 activities, A to H. A and E can start at the same time. A must finish before B starts. B must finish before C and F start. C must finish before D starts. E must finish before F and G start. F and G must finish before H starts. C and H must finish before D starts. Duration of: A = 5, B = 8, C = 15, D = 10, E = 6, F = 9, G = 19, H = 5. What is the critical path?

ABCD

ABFHD

EGHD

EFHD

Answer explanation

After drawing the network diagram EGHD is the longest path with 40 days

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The Customer requests the project manager to share the latest work performance report in WhatsAppmessenger as he is out on vacation. What should the project manager do next?

Immediately Share the report to the customer

Politely Deny sharing the report in WhatsApp Messenger as its unethical

Discuss the issue with the Team and Senior Management

Review Organization Process Assets to know Policies and Procedures

Answer explanation

Here in this scenario, the project manager should first review the OPAs to know the corporate policies and procedures for social media, ethics and security

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During a team meeting, a team member asks about the measurements that will be used on the project to judge performance. The team member feels that some of the measures related to activities assigned to him are not valid measurements. The project is BEST considered in what part of the project management process?

Initiating

Executing

Monitoring & Controlling

Closing

Answer explanation

The question states that the team member feels some of the measures on his activities are not valid. Therefore, he must be working during the executing phase of the project where project deliverables are produced and project members perform most of the work they should do

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During project execution, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?

WBS Dictionary

Activity List

Project scope statement

Scope management plan

Answer explanation

Work packages in a Work Breakdown Structure contain only nouns or a couple of words regarding work or deliverable. Detailed information on what needs to be done, responsibility, prerequisites, successors, due date, etc. are included in the Work Breakdown Structure Dictionary

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to:

Let the sponsor know of the stakeholders’ requests

Evaluate the impact of adding the scope

Tell the stakeholders the scope cannot be added

Add the work if there is time available in the project

Answer explanation

After the scope of a project is finalized and the scope baseline is determined, it can be changed only with the approved changed requests. If there is not an approved change request, the existing scope baseline must be valid and the project team must work on delivering that scope only. In the scenario, the scope is defined already but some stakeholders ask to add new work to the scope. This cannot be done unless there is an approved change request. Therefore, stakeholders must be informed that this new work cannot be added.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A schedule performance index, SPI, of 0.75 means:

Project is over budget

Project is ahead of schedule

Project is progressing at 75% of the rate originally planned

Project is progressing at 25% of the rate originally planned

Answer explanation

A is irrelevant because SPI is a schedule performance index. We cannot derive any conclusion about the budget performance of the project with this index. B is not correct because SPI is less than one, therefore, the project is behind schedule. And D, says that you have completed 25% of the work that you have originally planned, so it’s not correct. The correct answer here is C, because SPI 0.75 means, you have completed 75% of the work that you have originally planned.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?