For a decision tree analysis, the cost of executing a decision is $50,000. For the benefit part, there is 40% chance that the decision provides a return of $90,000 and 60% chance that the decision provides a return of $30,000. What is the expected monetary value for this decision?
CAPM Sample Exam

Quiz
•
Fun
•
Professional Development
•
Easy
Anna Doueihi
Used 4+ times
FREE Resource
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4,000$
28,000$
22,000$
12,000$
Answer explanation
EMV=[0.4x(90000-50000)]+[0.6x(30000-50000)]=4000 Since the EMV is positive, the decision can be taken
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your current project phase has 8 activities, A to H. A and E can start at the same time. A must finish before B starts. B must finish before C and F start. C must finish before D starts. E must finish before F and G start. F and G must finish before H starts. C and H must finish before D starts. Duration of: A = 5, B = 8, C = 15, D = 10, E = 6, F = 9, G = 19, H = 5. What is the critical path?
ABCD
ABFHD
EGHD
EFHD
Answer explanation
After drawing the network diagram EGHD is the longest path with 40 days
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The Customer requests the project manager to share the latest work performance report in WhatsAppmessenger as he is out on vacation. What should the project manager do next?
Immediately Share the report to the customer
Politely Deny sharing the report in WhatsApp Messenger as its unethical
Discuss the issue with the Team and Senior Management
Review Organization Process Assets to know Policies and Procedures
Answer explanation
Here in this scenario, the project manager should first review the OPAs to know the corporate policies and procedures for social media, ethics and security
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a team meeting, a team member asks about the measurements that will be used on the project to judge performance. The team member feels that some of the measures related to activities assigned to him are not valid measurements. The project is BEST considered in what part of the project management process?
Initiating
Executing
Monitoring & Controlling
Closing
Answer explanation
The question states that the team member feels some of the measures on his activities are not valid. Therefore, he must be working during the executing phase of the project where project deliverables are produced and project members perform most of the work they should do
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During project execution, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?
WBS Dictionary
Activity List
Project scope statement
Scope management plan
Answer explanation
Work packages in a Work Breakdown Structure contain only nouns or a couple of words regarding work or deliverable. Detailed information on what needs to be done, responsibility, prerequisites, successors, due date, etc. are included in the Work Breakdown Structure Dictionary
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to:
Let the sponsor know of the stakeholders’ requests
Evaluate the impact of adding the scope
Tell the stakeholders the scope cannot be added
Add the work if there is time available in the project
Answer explanation
After the scope of a project is finalized and the scope baseline is determined, it can be changed only with the approved changed requests. If there is not an approved change request, the existing scope baseline must be valid and the project team must work on delivering that scope only. In the scenario, the scope is defined already but some stakeholders ask to add new work to the scope. This cannot be done unless there is an approved change request. Therefore, stakeholders must be informed that this new work cannot be added.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A schedule performance index, SPI, of 0.75 means:
Project is over budget
Project is ahead of schedule
Project is progressing at 75% of the rate originally planned
Project is progressing at 25% of the rate originally planned
Answer explanation
A is irrelevant because SPI is a schedule performance index. We cannot derive any conclusion about the budget performance of the project with this index. B is not correct because SPI is less than one, therefore, the project is behind schedule. And D, says that you have completed 25% of the work that you have originally planned, so it’s not correct. The correct answer here is C, because SPI 0.75 means, you have completed 75% of the work that you have originally planned.
Create a free account and access millions of resources
Similar Resources on Quizizz
27 questions
FA Cup Quiz

Quiz
•
KG - Professional Dev...
30 questions
New Super Mario Bros. Wii Development [AI Generated]

Quiz
•
Professional Development
25 questions
MI Team Holiday Trivia Challenge

Quiz
•
Professional Development
31 questions
GLOBAL LEDGER dream of becoming in childhood

Quiz
•
Professional Development
25 questions
MARKETER QUIZ

Quiz
•
Professional Development
25 questions
Lean Six Sigma (English)

Quiz
•
Professional Development
32 questions
Ardour Mentorship Quiz

Quiz
•
Professional Development
35 questions
C3 (Cerdas Cermat Cepat) Challenge - HD 2021

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade