1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Product data submittals, samples, and _____________are required primarily for the architect and engineer to verify that the correct products will be installed on the project.

submittals

shop drawings

bid forms

addenda

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

samples should be stored at the jobsite and compared to

schedule

samples

materials delivered

jobsite layout

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

size and physical characteristics should be reviewed by both the contractors and the

owner

contractor

engineer

architect

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

the project manual typically includes

supplier

bid forms

materials

samples

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

the __________ are the base of reference for determining responsibility and liability for actions by the owner and contractor during the project period.

conditions of contract

labor agreement

mediation

none of the above

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

the design for construction projects is typically developed by the contractor and the architect. T/F

true

false

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

a ___________ is a drawing or set of drawings produced by the contractor, supplier, manufacturer, subcontractor, or fabricator

materials

samples

shop drawing

bid forms

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?