1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A small group of people with a combination of expertise or skills critical to the project is called the:

Project manager

Project team

Core project team

Board of directors

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a work breakdown structure (WBS)?

A WBS is a heirarchal structured grouping of project elements that organizes and defines the scope of the total project.

A WBS is a tool used to track the physical breakdown of a structure during demolition.

A WBS is a system used to organize employee work schedules and shift rotations.

A WBS is a database used to manage customer complaints and feedback for a business.

3.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Name following key WBS term

____ _______: This is the level at which the project manager can assign resources and track progress without getting bogged down in too much detail. As a rule of thumb, it should be small enough to assign to an individual or small team.

4.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Name following key WBS term

_______ account: This is typically one level above the work package. It is a level where costs are accrued, monitored, and used for management reporting.

5.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Name the following WBS term:

________ package: This is an undefined work package(s) below the control account used for planning known work when work package detail is not yet available. The planning package is a critical component of rolling wave planning.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Estimating cost, time, and resources are inputs into what document?

Stakeholder Register

Project Management Plan

Project Charter

Project Status Report

Answer explanation

A project management plan will contain the estimates generated from the WBS.

This document will provide a baseline from which to compare ongoing changes as well as making those changes more precise and easier.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Three-point estimates is a tool designed to assist the project manager in getting good estimates for duration, cost, effort, and resources.

(O + P) / 2 * ML

(O + ML) / 2

(O + ML + P) / 3

(O + 2ML + P) / 4

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development