PM2 23Spring Student Deemed Toughest PMI
Authored by Bobbie Jones
Business
10th Grade
Used 7+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
22 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In traditional plan-based project management, what constitutes a set of tasks that are required on a project, take time to complete, and use project resources?
Work Breakdown
Activity
Project
Deliverable
2.
MATCH QUESTION
1 min • 1 pt
Stands for Must have, Should have , Could have and Won't have (promotes common understanding)
Prioritization poker
When every task is assigned a priority
Product Roadmap
includes requirements and tactical steps as they are far more detailed
Delphi Technique
Teams decide most important stakeholders
Persona Technique
A problem solving technique which has anonymity as a benefit of brainstorming
MoSCow method
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which team role in agile project management is tasked to decide if an activity is needed?
Service Delivery Manager
Service Request Manager
Project Manager
Product Manager
4.
MATCH QUESTION
1 min • 1 pt
Difference between what time planned to spend and time did spend
Schedule Variance
Difference between what you planned to spend and what you did spend
Cost Performance Index
Determines if you are on budget
Schedule Performance Index
Determines if you are on time
Cost Variance
5.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which parts of the resource estimate process are considered to be outputs? (Choose Two)
Project Documentation Updates
Organizational Process Assets
Activity List
Activity Resource Requirements
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which statement best descibes the Product Owner role in a project?
Holds meetings daily in order to ensure consistency in communication
Maximizes the value of the product being made in a project
Ensures the stakeholders are as active as planned
Creates the RTM and assigns Tasks
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which type of backlog is a list of user-centric requirements that lists, in order, all the things that must be done to complete an entire project?
Product Backlog
Burndown List
Burnup Chart
Critical Chain
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?