1.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What is critical path method (CPM)
2.
MULTIPLE SELECT QUESTION
20 sec • 1 pt
It determines the earliest time each activity can start and finish and determines the total duration of the project.
Forward Pass
Backward Pass
Side Pass
Critical Path
3.
MULTIPLE SELECT QUESTION
20 sec • 1 pt
It determines the latest time each activity can start and finish without delaying completion of project. It also helps determine the activities that can be delayed or not.
Forward Pass
Backward Pass
Side Pass
Critical Path
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
What is CPM?
critical process method
critical path activity
Critical path method
critical process activity
5.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
Critical path in network gives ___ to complete the project.
Critical time
Longest time
Shortest time
Production time
6.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
In Critical Path Method, the project completion period is the EF of last activities.
True
False
7.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
Changing the duration of a critical activity will not affect the overall completion time.
True
False
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?