55 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
User testing on the last product release revealed low user interest in certain features that required a significant effort to develop. The team feels demoralized, and they want to make sure their future efforts are worthwhile. Success in the next iteration is critical as the competitor product is gaining market share. How should the team respond?
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project team is being sent overseas to lead an integration project at a subsidiary factory. To prepare, they review a transcript from the retrospective from a previous trip to identify the main problems. Which problem listed below can the team approach and potentially solve using servant leadership and active listening during the next iteration?
3.
MULTIPLE SELECT QUESTION
1 min • 1 pt
The team lead is having a coaching session with a team member. Read the scenario and answer the question. Lead: We've noticed that your work is a few days late again. Team Member C: It is. I took extra time to fine-tune settings before handing off to the release team. Lead: OK. We have been through this for the last four sprints, and we need to resolve it. After sprint 3, you blamed a faulty technical setup for the delay, but we found out that was not accurate. Do you think you can give us more realistic estimates next time? Team Member C: Yes, I was wrong. I thought I was giving realistic estimates, but I realize that after three sprints, my method must be flawed. Lead: Do you want to do a planning session together so we can figure out a better way? Team Member C: Yes, that would be helpful. I know that my delay is causing stress on the team. Thanks! Which two steps in emotional intelligence (EI) has this team member just realized? (Choose two)"
4.
MULTIPLE SELECT QUESTION
1 min • 1 pt
To improve its culture for workers, an organization’s leadership team wants to provide childcare services. Other personal services such as wellness and financial counseling are planned for the next calendar year. The project team needs to decide how to implement the new services. Leadership wants these services in place as soon as possible. The team holds a brainstorming session. Which two questions should the team explore to begin implementation of the services? (Choose two.)
5.
MULTIPLE SELECT QUESTION
1 min • 1 pt
A project’s goal is to improve a company’s customer service process through automation and staff development. The team sent initial surveys to the staff to assess their satisfaction with the current process and are now analyzing the responses. These are the top four responses: • The current process works fine. • The current process needs fixing. • We need better training. • We do not need any more training. Which two activities should the project team perform first? (Choose two)
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager has drafted a project management plan. While working with the stakeholders, the project manager observes that the key stakeholder’s priorities for the scope and schedule are vastly different from the priorities of all of the other stakeholders. Key stakeholder - site upgrades and user improvements in a 9-month project schedule. Stakeholders F, K, and S - user improvements in a 3-month project schedule. Stakeholder A has openly stated that the broader scope and longer schedule are necessary for project success. What should the project manager do first in order to get this project management plan approved?
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
An agile team has identified several risks during their last retrospective, including the chance of hiring a contractor to double the speed of a critical investigation during the next iteration. How should the team classify this risk?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
60 questions
Cutting Edge Pre-Intermediate Units 5 - 8
Quiz
•
12th Grade - Professi...
50 questions
SYNONYMS AND ANTONYMS
Quiz
•
Professional Development
50 questions
English Proficiency test A1+
Quiz
•
Professional Development
50 questions
ALC Book 1-3 Reading Review
Quiz
•
Professional Development
50 questions
CTTAOA English diagnostic test.1
Quiz
•
Professional Development
50 questions
English Test
Quiz
•
University - Professi...
55 questions
RIDDLES
Quiz
•
KG - Professional Dev...
50 questions
Времена группы Simple
Quiz
•
Professional Development
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for English
20 questions
Black History Month Trivia Game #1
Quiz
•
Professional Development
100 questions
Screening Test Customer Service
Quiz
•
Professional Development
20 questions
90s Cartoons
Quiz
•
Professional Development
10 questions
Reading a ruler in Inches
Quiz
•
4th Grade - Professio...
16 questions
Parallel, Perpendicular, and Intersecting Lines
Quiz
•
KG - Professional Dev...
12 questions
Valentines Day Trivia
Quiz
•
Professional Development