Search Header Logo

10A PMI - 2

Authored by Chris Nguyen

English

Professional Development

Used 1+ times

10A PMI - 2
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Due to regulatory changes, a government agency is now a key stakeholder on a complex project. The project manager wants to develop an understanding of this new project stakeholder and any new high-level risks. What should the project manager use?

Meetings
Assumption log
Stakeholder engagement plan
Benefits management plan

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is ready to close a project. What should the project manager do next?

Resolve all project risks to ensure that the deliverables will be accepted.
Manage quality to validate that the deliverables have met standards.
Measure the project deliverables against the project charter and request customer acceptance.
Review the project management plan to ensure the scope's completion and request customer acceptance.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project is completed, and closeout activities are underway. The project manager discovers that a team member is performing operations activities unrelated to the project scope, but necessary for regular operations. Since the final deliverables must be handed over to operations, what should the project manager do?

Train a resource from operations to perform the activities.
Issue a change request and obtain approval from the change control board (CCB).
Temporarily transfer the team member to operations.
Ask the team to assist in completing the operations work and close the project.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project has ended; however the project manager and project team members are still called to solve technical issues, make some small changes, and evaluate new requirements. What should the project manager do to guarantee the product or service developed by the project now has operational support?

Obtain project acceptance.
Perform a project handoff.
Disband the project team and find a new project.
Fulfill all remaining needs as the product is still under development.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager learns that a new law, which will affect the business' type of products, is expected to be passed within the next three to six months. A project to launch a new product is being initiated, and is expected to be complete within two-and-half months. This new product would not meet the requirements of the proposed legislation if it passes. What should the project manager do?

Meet with the sponsor and key stakeholders to discuss the risks, then update the assumption log and project charter based on the results of that meeting.
Advise the project sponsor and stakeholders to cancel the project until the legislation comes into effect.
Ensure that the product is completed without any delays so that it is unaffected by the potential change in legislation.
Continue to plan the project, but update the risk management plan.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a demo and review meeting, the progress report shows that an agile project is not on track. The project manager is surprised, because all work was purposely selected and sequenced to meet higher-level objectives. What should the project manager have done to prevent this miscommunication?

Trained and mentored the team on using the agile approach
Engaged the team to record the agile progress reporting system
Created a contingency reserve
Encouraged the team to self-organize and provide buy-in to the project

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Due to scope changes during project execution, the project manager identifies that a provider must make changes to a product module already in use. What should the project manager do first?

Check the procurement management plan and the contract terms.
Update the risk register and issue log with this information.
Negotiate directly with the provider to reach an agreement
Prepare a change request to update contract terms with the provider.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?