CHAP 7.PRM

CHAP 7.PRM

University

45 Qs

quiz-placeholder

Similar activities

IT INFRA-MIDTERM EXAM

IT INFRA-MIDTERM EXAM

University

50 Qs

SPM Revision IV

SPM Revision IV

University

50 Qs

BCS Level 4 Software Development Methodologies

BCS Level 4 Software Development Methodologies

University

41 Qs

Project Monitoring and Close-Out Quiz

Project Monitoring and Close-Out Quiz

University

40 Qs

IS210 - Midterm Exam

IS210 - Midterm Exam

University

40 Qs

MS101 - Quiz 1 Midterm

MS101 - Quiz 1 Midterm

University

50 Qs

System Integration-Midterm Exam

System Integration-Midterm Exam

University

40 Qs

Quiz SPM 7

Quiz SPM 7

University

49 Qs

CHAP 7.PRM

CHAP 7.PRM

Assessment

Quiz

Computers

University

Easy

Created by

Nguyen Doan Hanh Linh

Used 4+ times

FREE Resource

45 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The additional percentage or dollar amount by which actual costs exceed estimates is called the cost ____.
excess
availability
completion
overrun

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

EVM stands for ____ value management.
excess
earned
eventual
economic

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Project ____ management includes the processes required to ensure that a project team completes a project within an approved budget.

cost

time frame

time frame

goal

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

____ planning involves determining what people, equipment, and materials a project team should use to perform project activities and the quantities of each resource.
Scope
Cost
Resource
Development

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The output of the resource planning process is a list of resource ____.
goals
requirements
ideas
plans

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Cost ____ involves developing an approximation of the costs of the resources needed to complete a project.
budgeting
control
estimating
planning

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The main outputs of the cost estimating process are cost estimates, ____ detail, and a cost management plan.
development
budget
scope
supporting

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?