Great 1-1

Great 1-1

Professional Development

50 Qs

quiz-placeholder

Similar activities

Great 2-3

Great 2-3

Professional Development

50 Qs

A1_Quiz 1

A1_Quiz 1

Professional Development

45 Qs

Partial 2 - Test for the 9-10 class

Partial 2 - Test for the 9-10 class

Professional Development

45 Qs

EN Elementary - Day 8 Vocabulary

EN Elementary - Day 8 Vocabulary

Professional Development

50 Qs

Great 5-1

Great 5-1

Professional Development

50 Qs

A1_A2_Word Formation_Week 4

A1_A2_Word Formation_Week 4

Professional Development

50 Qs

Software Engineering Quiz

Software Engineering Quiz

Professional Development

45 Qs

BUSINESS ENGLISH COLLOCATIONS ( DO - MAKE - TAKE)

BUSINESS ENGLISH COLLOCATIONS ( DO - MAKE - TAKE)

Professional Development

46 Qs

Great 1-1

Great 1-1

Assessment

Quiz

English

Professional Development

Hard

Created by

Chris Nguyen

Used 5+ times

FREE Resource

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value. What should the project manager pay special attention to in order to achieve this goal? Question 1Select one:
Reviewing and updating the requirements management plan
Carrying out quality audits and failure analyses
Monitoring the work breakdown structure (WBS)
Monitoring and updating the benefits realization plan

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A new agile team is forming and the project manager notices that the team is struggling in many areas. The team is experiencing both the inability to meet iteration commitments and team member conflicts. What should the project manager do next? Question 2Select one:
Raise the issues in the retrospective and propose solutions
Inform management that commitments will not be met.
Involve management to help resolve the conflicts
Coach the team both as a whole and individually

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed. What should the project manager do? Question 3Select one:
Add the competitor's functionalities to the product backlog to improve the product
Ask the sponsor to add more people to the team
Help the team to find a new approach to launch the product as soon as possible
Ask the team to increase the velocity to launch the product as soon as possible

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value. What should the project manager have done to avoid this perception? Question 4Select one:
Involved the business stakeholders in the sprint review
Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits
Implemented a closing survey for key stakeholders
Confirmed that there is a communications management plan in place to make business stakeholders aware of the success

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project. What should the project manager do? Question 5Select one:
Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.
Stop crashing the schedule
Manage the project sponsor closely and revise the project's resource management plan to improve indicators
Use a resource-levelling technique

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25. The project manager must provide the first project status review soon and wants to emphasize that the project is under control. How should the project manager report the project status to key stakeholders? Question 6Select one:
Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results
Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.
Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.
Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again. What should the project lead do next? Question 7Select one:
Notify senior management of the issues and have them review the importance of agreements with the team
Challenge the team to determine if the issues surfaced again because agreements were not followed
Post the agreements in a conspicuous place where all of the team members can see them.
Let the team self-organize and determine the best means to prevent the issues from occurring again

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?