1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

While working on a poorly defined internal project, a project manager receives multiple change requests from senior management. What should the project manager do first?

Identify how the proposed changes will benefit the project in relation to the business case.
Ask for a temporary budget increase to avoid cost overruns.
Keep the team motivated and incentivized to avoid exhaustion from working on a lengthy project.
Assess the schedule delay and begin implementation to avoid additional lags

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback. What should the project manager do to resolve the issue?

Move one of the team members to a different protect team
Review the ground rules for collaboration within the team
Report the performance issue to both of the team members' supervisors
Modify the communications management plan and resend it to the team

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A key resource is newly assigned to a project. The project manager and the resource did not get along well in a previous project. This resource is needed to ensure the completion of a major component for the project. What should the project manager do?

Work on resolving the differences with the key resource and building a good working relationship to ensure project success.
Monitor the key resource closely throughout the project, but do not let the project sponsor know about the conflict.
Request that the key resource's functional manager work directly with the resource during the project.
Discuss this with the project sponsor and request that this key resource be replaced on the project.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is leading an automation project. The project team is colocated and includes people from both the technical and business units. The project manager discovers that personal differences and work styles are affecting the project negatively. How should the project manager address this?

Develop a schedule that ensures people with personal differences work separately.
Use an approach to the project that does not involve colocation.
Meet with the team and agree on expectations from team members.
Invite the functional managers of the different units to address their personal differences.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release. What tools should the agile project manager use to do these estimates?

Product backlog, budget, resource management plan
Budget, minimum viable product (MVP), retrospective notes
Resource management plan, retrospective notes, backlog grooming
Backlog grooming, product backlog, minimum viable product (MVP)

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In the planning phase, a project manager receives identified risks from the sponsors and subject matter experts (SMEs) and wants to develop a risk response strategy for them. What should the project manager do first?

Perform a risk reserve analysis.
Assign allocated budget to cover key risks.
Agree on the criteria to prioritize risks.
Assign a risk responsibility to each team member.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager notices that the response action for an identified issue is insufficient for solving the problem. What should the project manager do next?

Include the issue in the risk register and update the team
Document the continuing issue and failed solution
Inform the stakeholders about the failure and update the issue log
Meet with the project team to find another solution

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?