Procurement of Goods

Procurement of Goods

Professional Development

6 Qs

quiz-placeholder

Similar activities

TayNew Review (Multiple Choice)

TayNew Review (Multiple Choice)

Professional Development

10 Qs

Post test phase 1st (Day 1st)

Post test phase 1st (Day 1st)

Professional Development

10 Qs

Chest Radiography

Chest Radiography

Professional Development

10 Qs

Blood smears

Blood smears

Professional Development

10 Qs

DC MOTOR

DC MOTOR

Professional Development

10 Qs

distribution channels

distribution channels

University - Professional Development

8 Qs

Davis & Shirtliff Founders' Day Trivia

Davis & Shirtliff Founders' Day Trivia

Professional Development

11 Qs

Quiz on Freedom Fighters On Inida

Quiz on Freedom Fighters On Inida

KG - Professional Development

11 Qs

Procurement of Goods

Procurement of Goods

Assessment

Quiz

Specialty

Professional Development

Medium

Created by

Lidya Rahayu

Used 2+ times

FREE Resource

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

Threshold Procurement of Goods

Direct Award < EUR 1.000 should be executed by

 staff members with approval from officer responsible for the budget

PROJECT

TENDER

CP UNIT

Answer explanation

Media Image

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If materials and equipment worth up to EUR 50,000 procured through a public tender, do we need to obtain approval from HQ prior executing the tender?

NO.

HQ Approval not required

YES

HQ approval is a must for procurement above EUR. 20.000

Answer explanation

If materials and equipment worth up to EUR 50,000 are procured through a public tender, coordination with the Procurement and Contracting Division is not required. ProSoft does not have to be used to obtain approval for the award procedure to be used and for the order.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  1. The following task are performed by?

  2. 1. Drawing up the specification

  3. 2. Checking the budget

  4. 3. Selecting the materials and equipment/ calculating the planned cost

  5. 4. Inspection of incoming goods and issuing formal acceptance of the goods.

CP Officer

Office Assistant

Receptionist

officer responsible for the commission

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Are you allowed to take environmental impact into account when assessing bids?

YES,

choosing environmental friendly goods are number one rules.

NO.

GIZ has to prioritize cost when buying supplies and meeting environmental criteria generally more expensive

YES,

as long as the environmental criteria are clearly set out in the invitation to tender

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many personnel in CP Unit?

9

8

10

8.5

Answer explanation

  1. 1. Mba Swes

  2. 2. Om Danar

  3. 3. Uni Vera

  4. 4. Mpok Amel

  5. 5. Mpok Diany

  6. 6. Bang Irvan

  7. 7. Mba Dewi

  8. 8. Noni Jata

  9. 9. Mas Joko

  10. 10. Dede Lidya

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Shortly after you place an order, the supplier contact you to explain that it cannot deliver until three weeks after the PO agreed date. What should you do?

Cancel the PO and replace with the 2nd rank.

Nothing we can do, except wait the items deliver

Set an extended deadline for delivery. We could also threaten to impose a contractual penalty if this clearly mentioned on the PO

black list the supplier