TechMD -IEC Module 2 Quiz

TechMD -IEC Module 2 Quiz

Professional Development

10 Qs

quiz-placeholder

Similar activities

Module 8210 Last check POAET AV 21/001

Module 8210 Last check POAET AV 21/001

Professional Development

8 Qs

 Nissan Patrol Quiz

Nissan Patrol Quiz

Professional Development

15 Qs

WCM - Chpt2

WCM - Chpt2

Professional Development

13 Qs

Quizz E-Invoicing

Quizz E-Invoicing

Professional Development

10 Qs

HIV 1001

HIV 1001

Professional Development

13 Qs

Cannock Electricity Supply  Quiz

Cannock Electricity Supply Quiz

Professional Development

7 Qs

THE MUGHAL EMPIRE QUIZ

THE MUGHAL EMPIRE QUIZ

7th Grade - Professional Development

15 Qs

ETFO Quiz

ETFO Quiz

Professional Development

7 Qs

TechMD -IEC Module 2 Quiz

TechMD -IEC Module 2 Quiz

Assessment

Quiz

Other

Professional Development

Medium

Created by

Phoebe Adriano

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The trial operation policy does not apply to:

newly commissioned substation primary equipment

newly commissioned and energized secondary devices.

newly commissioned transmission lines

all of the above

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

refers to the “under observation” period wherein the performance, quality, and suitability of the newly commissioned substation primary equipment and/or transmission lines must be assessed.

Grace period

Operational procedure

Trial operation

none of the above

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Shall undergo a Trial Operation of 24 hours before loading and another

48 hours after loading, starting from the commissioning date

Substation Primary Equipment

Transmission Lines

Secondary devices

all of the above

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

This shall undergo a trial operation for a period of 72 hours starting from its energization on the commissioning date.

Substation primary equipment

Transmission line

Secondary devices

all of the above

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is ELTON?

Eligibility to Lead Transmission Outages and Nuisance

Encouragement Leading to Transmission Outages and Nuisance

Enroachment Leading to Transmission Outages and Nuisance

none of the above

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The Circular deals with the control and prevention of small Animal, Birds and Insect Intrusions Inside Substations.

Circular No. 2010-0040

Circular No. 2010-0001

Circular No. 2010-0004

Circular No. 2010-0043

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

From 2017 - June 2022 statistics, how many percent do snake intrusion-related outages account for?

60%

70%

25%

82%

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?